Between the remedial action's start on September 30, 2020 and demobilization on September 4, 2021, 50,400 cubic yards of contaminated sediment were removed from the lower 1.7 miles of Otter Creek, in northwestern Ohio. This is the story of the Duck and Otter Creeks natural resource damage case, as the U.S. Fish and Wildlife Service tells it.
The creeks and what polluted them
Duck and Otter Creeks lie just east of the Maumee River, in its urbanized watershed, and both flow into Maumee Bay on Lake Erie. Decades of industrial activity nearby released hazardous substances that contaminated soils, sediments and surface water. The contaminants of concern are polycyclic aromatic hydrocarbons (PAHs), polychlorinated biphenyls (PCBs), metals including arsenic, and other organic contaminants.
How the assessment works
Under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), a federal trustee studies the harm to natural resources through a Natural Resource Damage Assessment and Restoration (NRDAR) process. Here the Department of the Interior, acting through the Fish and Wildlife Service, is the trustee for federal natural resources and began the assessment in 2010.
- The trustee invited the potentially responsible parties to a cooperative assessment, but they declined.
- A Pre-Assessment Screen, a rapid review of readily available information on the releases and possible harm, found that an assessment was warranted.
- An Assessment Plan was prepared in 2010 to set out how to assess and quantify injuries, to work out how much restoration is needed. Natural resources provide services such as food and shelter for wildlife.
- The assessment phase is ongoing: injury determination, injury quantification, restoration scaling and damage determination. Damages are measured as the cost of restoring, rehabilitating, replacing or acquiring the equivalent of the injured resources and their services, plus the trustee’s assessment and restoration-planning costs.
Dredging Otter Creek
A stretch of Otter Creek was cleaned up through a public/private partnership under the Great Lakes Legacy Act (GLLA), which aims to speed up removal of contaminated sediment in Great Lakes Areas of Concern and was revised in 2008 to include habitat restoration. The trustee notes that habitat restoration does not always occur and may be limited in extent, so it may not fully replace the injured natural resources.
An amendment signed in July 2020 between the EPA Great Lakes National Program Office and three industrial partners (BP Husky Refining and BP Remediation Management Services, Chevron Environmental Management Company, and Evergreen Resources Management Operations, also called Sunoco), known together as the Otter Group, funded the cleanup with EPA. Work began on September 30, 2020. Hydraulic dredging removed 50,400 cubic yards of contaminated sediment from the lower 1.7 miles of the creek and its confluence with Maumee Bay. The site was fully demobilized on September 4, 2021.
Settlement and restoration
The trustee has reached a proposed settlement with several of the potentially responsible parties, while the United States continues to seek resolution with the rest. Under it, money will pay for a portion of the Delaware/Clark Island Complex Restoration Project. A draft Restoration Plan and Environmental Assessment was open for public comment from January 9 to February 8, 2024. No comments were received, and the final plan was released in March 2024.
Sources
- U.S. Fish and Wildlife Service, “Duck and Otter Creeks Natural Resource Damage Assessment and Restoration,” https://www.fws.gov/project/duck-and-otter-creeks-natural-resource-damage-assessment-and-restoration-0; rewritten in hubnx's own words.