"Mitigation" usually suggests softening something harsh. In the Bureau of Land Management's policy it means something more forward-looking: a way to authorize uses of public land while protecting resources and making sure projects deliver long-term benefits. It supports the agency's work managing public lands for multiple use and sustained yield, and gives project proponents more predictability and a chance to become partners in managing resources.
Old tools, new consistency
For decades the BLM used avoidance and minimization to reduce harm to public land resources. Since the early 2000s it has also required compensation, known as compensatory mitigation, at the project level for impacts that are very hard or impossible to avoid or minimize. The current policy builds on what those experiences taught and sets one consistent group of principles and procedures for including mitigation in BLM decisions.

Lek buffers, shown as light-green circles, are a way to avoid impacts to greater sage-grouse when authorizing rights-of-way (blue-black and red lines) and other surface-disturbing uses. Image from BLM's page.
The mitigation hierarchy
Mitigation weighs conserving natural and cultural resources for the future against the benefits of use and development now. It follows a sequence called the mitigation hierarchy:
- Identify the impacts of a proposed use.
- Avoid impacts where possible.
- Minimize impacts that cannot be avoided.
- Finally, work out appropriate compensation for the impacts that remain.

The steps are applied in order during impact analysis under the National Environmental Policy Act (NEPA). Image from BLM's page.
Planning ahead
Thinking about mitigation well before deciding on any individual use is key. Land use plans identify resources in an area that are especially important, scarce or sensitive, or that have protection under a law such as the Clean Water Act, the Endangered Species Act or a state law. Writing mitigation opportunities, and the standards for judging whether they work, into approved resource management plans can produce long-term benefits at the landscape scale. The remaining steps then happen in the project-level environmental review that comes before a decision on a particular use.
When the BLM requires a project sponsor to carry out mitigation as a condition of authorization, it identifies the impacts tied to each measure and explains how the measure avoids, minimizes or compensates for them. All mitigation should have measurable, durable effects that can be adjusted as needed to meet resource objectives.
Sources
- Bureau of Land Management, "Timely measures: Mitigation policy for multiple use and sustained yield"; https://www.blm.gov/blog/2022-01-19/timely-measures-mitigation-policy-multiple-use-and-sustained-yield; rewritten in hubnx's own words.