Автора пока нетВзять себе
- Лицензия
- CC BY-SA 4.0По материалам www.appropedia.org
- Языки
- English

The finished greenhouse after the 2020 repairs. Photo: Soysinlimites on Appropedia, CC BY-SA 4.0.
The big job in this greenhouse was plaster: 303 of the project's hours went into stucco on the straw bale walls, and the filler layer alone took approximately 120. The builders, who wrote the project up on Appropedia, are two building partners: the author and Scott. Both wanted a career in alternative building and chose a small greenhouse as a place to start. It was for Kiva, who wanted to grow chili peppers, tomatoes and other warm-weather plants.
The design
Where they live, no permit is needed for a greenhouse of 10 by 12 feet, so they made that the inside size. Two walls are straw bale, the north and west ones, and two are wood and glass. For the best year-round sun the glass on the south wall is set at 40 degrees. The site gets plenty of morning sun and little in the evening, so the east wall is glass and the west wall is straw. Straw was chosen to gain experience with it and for its insulation.
Building it
- Foundation. The yard slopes, so they dug down about three feet at the far side and moved the soil by hand, which took far longer than expected; the author would now rent a small bulldozer. The northeast corner was all clay after the first foot and a half and took almost as long as the rest. The straw sides have a foundation 18 inches wide so a bale can lie on its side without overhanging. They used about two and a half yards of premixed concrete, poured down a piece of stovepipe from the recycling center, and pushed L-shaped rebar into the north and west sides to hold the bales.
- Frame and roof. Rafters are 2x4s rather than the usual 2x6s, and straw infill meant the walls needed 152 fewer board feet of 2x4. A French drain runs around the foundation. The roof is a cardboard-shaped plastic with an R-value of about 2.5, better than the uninsulated corrugated fiberglass usually used. The glass went on harder than expected, and the special caulk was a mess. With hindsight, they would space the rafters wider so a strip of wood could be screwed down between sheets of glass.
- Windows. All were recycled, bought locally. The east window was made to be mounted upright, and on its side its springs made it hard to close (they removed them) and its drains ended up at the side, causing a leak.
- Bales. They used three-string bales of rice straw, 18 in all, and stacked them on pallets first. Rebar pushed through the layers pins them. A garden shear cut bales better than a saw, and a copper baling needle, made from an old grounding rod, let them shorten about seven bales; retied with a trucker's hitch. A 2x4 laid on top with a person hanging from each end pressed the top bales tight. Top plates made like ladders, plus wire cables with turnbuckles, hold the walls in place, and every crack was stuffed with straw.
Plaster, layer by layer
| Layer | What it is | Notes |
|---|---|---|
| Clay slip | Screened clay soaked and blended to a creamy texture | 50 gallons, sprayed on with a rented plaster sprayer; gives the next layers something to bind to |
| Scratch coat | Sand, clay and straw, like brownie mix | Applied by hand, bottom to top, then scored with fingers |
| Filler coat | Same materials, less clay and water, longer straw | Mixed with feet on tarps, pressed on in hand-sized balls onto a damp wall; about 120 hours |
| Last coat | Horse manure, clay, sand and flour paste | Sand through a 1/8-inch screen, manure through 1/4 inch; a university class helped |
The first try at the last coat had too little sand and manure and cracked, so it was redone. The final mix was two parts sand and horse manure to one part clay, with plenty of water. Their advice is to make test strips about twice as big as they did and to get the proportions right before committing.
Hours and money
The authors counted time as the hours one person would need. The biggest items:
| Task | Hours |
|---|---|
| Stuccoing | 303 |
| Building the frame | 68 |
| Digging | 34 |
| Pouring concrete | 32 |
| Bales | 32 |
| Shopping | 30 |
The largest costs were wood ($670), roofing ($345), concrete ($316), hardware ($314), windows ($240) and straw bales ($174). The page's printed totals do not match its own line items, so no total is given here. Their main advice is to plan, plan, plan: a detailed design and cost estimate would have saved a good deal of money lost to hidden costs. The cob filler layer was the other big problem, and they hoped for a better way to seal bales. Not all went wrong: the trucker's hitch, the rented cement mixer and a texturing gun for the slip all paid off. And people who walked past stopped to ask about it, which built a sense of community. Kiva has grown tomatoes and peppers with ease there.
What went wrong later
- First year. The first bale sat a little out of line and left a dip; loose straw would not hold stucco, so they cut the section out and rebuilt it over peg board, tied on and coated with a thin mix of cooked flour, horse manure and sand. The two lower south windows had been installed upside down, so they made wooden stoppers. In the fall rains the southwest corner leaked straight into the bale wall, where moisture rots straw. They found a leak at the top, where water got between siding and bale, and another where the window was not sealed down to the foundation. They removed the wet straw, let it dry for about a month under a tarp, sealed the window to the foundation and added a rain gutter. No more leaks followed.
- Year two. The retaining wall stopped short of the ground and let soil in; a board added at the bottom fixed it. They covered the exposed rafter ends with extra roofing, and found every screw in the roof leaking, so each was backed out, ringed with silicone and tightened.
- 2010. The sideways window slipped out of its track and blew out and broke in a storm. A recycled window made to lie on its side replaced it without trouble.
- 2020. After many years the roof leaked and wood had rotted. They took off the roof, gutter, siding and rotten wood, replaced the wood and siding, painted the rafters and door, resealed the windows and fitted a new roof and front gutter.

Painting the rafters. Photo: Soysinlimites on Appropedia, CC BY-SA 4.0.

New siding up and the new roof going on. Photo: Soysinlimites on Appropedia, CC BY-SA 4.0.

The 2025 growing season: hanging tomatoes, basil, cucumbers, peppers and marigolds. Photo: Soysinlimites on Appropedia, CC BY-SA 4.0.
Sources
- Appropedia contributors, Kiva's straw bale greenhouse, Appropedia, licensed CC BY-SA 4.0; photographs by Soysinlimites, also CC BY-SA 4.0. Changed here: condensed and reworded, with the source's own figures and totals left out; rewritten in hubnx's own words. This page stays under CC BY-SA 4.0.