Why did Neil Armstrong, and not Buzz Aldrin, plan to step onto the Moon first? NASA’s Apollo Spacecraft Program Manager announced the answer in April 1969, and it was logistics: the Lunar Module’s hatch opened inward, so Aldrin would have had to climb over Armstrong in the cramped cabin, both in bulky spacesuits. That month NASA continued preparing to meet President Kennedy’s goal of landing a man on the Moon and returning him safely before the end of the decade. Program managers were becoming confident that Apollo 11 in July would make the first landing, provided all went well on Apollo 10 in May, essentially a rehearsal of the landing.

In the Manned Spacecraft Operations Building (MSOB), workers complete attaching the landing legs to the Apollo 11 Lunar Module (LM) and prepare to mate it with its Spacecraft LM Adapter (SLA).
Stacking the spacecraft
In the Kennedy Space Center’s MSOB, workers attached the four landing legs to the Apollo 11 LM and mated it with its adapter on April 4. Three days later they finished assembling the spacecraft by adding the Command and Service Modules. On April 14 they moved it to the Vehicle Assembly Building (VAB), where engineers stacked it on its Saturn V rocket. Tests of the vehicle followed, before its rollout to the launch pad in mid-May.

In the VAB, the Apollo 11 spacecraft is lowered onto its Saturn V rocket.
Who goes first
On April 14, George M. Low, Apollo Spacecraft Program Manager, said at a press conference that Commander Neil A. Armstrong would most likely be the first person to exit the LM and take humanity’s first steps on the lunar surface. Lunar Module Pilot Edwin A. “Buzz” Aldrin would follow about 20 minutes later. The main reason was the inward-opening hatch described above. Command Module Pilot Michael Collins was to stay in lunar orbit during the landing.
Crew training
The crew tested their spacesuits (Extravehicular Mobility Units) in the 8-foot altitude chamber at the Manned Spacecraft Center (MSC), now the Johnson Space Center in Houston. On April 14, Collins used the centrifuge in MSC’s Building 29 to practice the profiles of a launch and a reentry from a lunar mission. On April 18, in Building 9, Armstrong and Aldrin, in their suits, completed a 2.5-hour simulation of surface activities such as collecting rock and soil samples and deploying scientific instruments.

Armstrong practicing taking the first step onto the lunar surface.

Aldrin (left) and Armstrong during surface EVA training.
Testing the lander
To certify the LM for the loads of a lunar landing, engineers at MSC continued drop tests with the flight-like LM-2 in the Vibration and Acoustics Test Facility. The series began in late March, and three of the five tests were done in early April. They induced lateral accelerations on the wire harnesses and plumbing in the aft equipment bay, high acceleration loads around the inertial measurement unit and the environmental control system, and stress on the LM's front face and side hatch. The final test, in early May, completed the LM’s certification for the first lunar landing.

One of the three LM-2 drop tests conducted during the first week of April.
The Lunar Receiving Laboratory
At MSC, staff were preparing the Lunar Receiving Laboratory (LRL) for the return of the astronauts and lunar samples. It was built to isolate astronauts, their spacecraft and the rock samples to prevent back-contamination of Earth by any possible lunar micro-organisms, and to keep the samples as pristine as possible. Long simulations of its main functions, including the Crew Reception Area, were completed in early April and exposed deficiencies: problems with the sterilization equipment, and the gloves used in gloveboxes repeatedly developed holes that compromised the biological barrier. A readiness review on April 17–18 noted these too. MSC Director Robert L. Gilruth put his special assistant Richard S. Johnston in charge of all aspects of the LRL. The problems were corrected, and the LRL was certified just before the Apollo 11 mission.
The lunar landing trainer
At Ellington Air Force Base near MSC, the Lunar Landing Training Vehicle (LLTV) resumed flights on April 7 with MSC pilot Harold “Bud” Ream at the controls. It was a key tool for astronauts to practice the flying characteristics of the LM, especially the final 500 feet of the descent. NASA managers had grounded it after two separate crashes and, after investigations, allowed flights to resume, but only by test pilots. Ream flew more than a dozen flights into early June before managers cleared it for astronaut training. Armstrong finished his training flights one month before flying the LM for the first lunar landing and credited much of the landing's success to that training.

LLTV-2 test flight April 23.
Sources
- NASA, Apollo 11 Preparations in April 1969, NASA History; rewritten in hubnx's own words.