The Saturn V nears the Vehicle Assembly Building (VAB) at NASA's Kennedy Space Center during the rollback. Image from NASA's page.
The Saturn V that rolled back from Launch Pad 39A to the VAB on January 27, 1972 was only the second Moon rocket to return to the building while at the pad for testing, and the one and only time with a flight vehicle. The first was in June 1966, to keep the Saturn 500F test vehicle out of the way of an approaching hurricane. This time the cause was a fuel tank in the Command Module damaged during a test, after Apollo 16's launch had already slipped a month.
Three reasons for a one-month slip
On January 7, NASA managers announced that the launch would move from March 17 to the next opportunity, April 16, for three reasons:
- Testing of changes to the spacesuits worn by John Young and Charles Duke, so they could bend more easily to pick up samples, would not be done in time.
- Extensive testing of the Command Module's docking ring jettison device was needed after it failed in a test for the Skylab program.
- Engineers wanted more data to reverify the Lunar Module battery's capacity.
All of that was finished to meet the April date. Doctors did not expect Duke's illness to affect the original date, but the delay gave Duke more time to recover. He had begun to feel ill on the crew's December 1971 geology field trip to Hawaii, flew to Kennedy on January 3, and was diagnosed the next day with double bacterial pneumonia. He spent a week in the Patrick Air Force Base hospital while the rest of the crew carried on with their activities. NASA released an updated preliminary timeline on January 10.
The rollback
On January 25, during a test at Pad 39A, workers accidentally over-pressurized a fuel tank in the Command Module's reaction control system. The damaged tank had to be replaced, and that could not be done at the pad.

The Apollo 16 Saturn V begins its rollback from Launch Pad 39A. Image from NASA's page.
In the VAB workers removed the Launch Escape System tower, then destacked the spacecraft and trucked it to the Manned Spacecraft Operations Building (MSOB). There technicians separated the Command Module from the Service Module, removed its heat shield and replaced the tank. They then reversed the process, stacked the spacecraft on the Saturn V and rolled the assembled vehicle back to the pad in two weeks, in time for April 16.

Workers destack the spacecraft from the Saturn V in the VAB. Image from NASA's page.

The spacecraft leaves the VAB for the MSOB. Image from NASA's page.

In the MSOB, workers lift the Command Module from its Service Module to replace the damaged tank. Image from NASA's page.
The crew kept training
The crew was Young as commander, Thomas Mattingly as Command Module pilot and Duke as Lunar Module pilot, with Fred Haise, Stuart Roosa and Edgar Mitchell as their backups. They trained for the fifth lunar landing, a 12-day mission to the Descartes site in the Moon's highlands, with extensive simulator work and preparation for three lunar surface traverses and orbital observations.

The three planned lunar surface traverses at Descartes. Image from NASA's page.
- Mattingly held a press conference on January 6 about his role: he would stay in orbit making visual and photographic observations and using the Scientific Instrument Module bay's instruments while Young and Duke explored the surface.
- Mattingly and Roosa practiced the deep-space spacewalk to retrieve film cassettes from the instrument bay in the Water Immersion Facility.
- Young and Duke and their backups rehearsed lunar surface activities, including driving the Lunar Roving Vehicle at Kennedy. Young and Haise practiced the descent and landing with the Lunar Landing Training Vehicle at Ellington Air Force Base.
- The backup crew did water egress training in the Gulf of Mexico on January 22, and the prime crew finished it two weeks later. All received extensive geology briefings.
Elsewhere at the Manned Spacecraft Center that month
- Apollo 17: Eugene Cernan and Harrison Schmitt, with support astronauts and geologists, went on a two-day geology field trip to Boulder City, Nevada, practicing their second and third lunar traverses with Explorer, a ground-based trainer for the Lunar Roving Vehicle. Their crewmate Ronald Evans flew over the area to review the traverses against the regional geology, as he would from lunar orbit.
- Lunar Science Conference: from January 10 to 13, more than 600 scientists from the U.S. and 13 other nations attended the third annual conference, held at the Manned Spacecraft Center for the first time. Soviet delegates discussed results from Luna 16 and Lunokhod 1, and NASA gave the Soviet delegation three grams of lunar soil brought back by Apollo 14.
- Leadership: on January 14 Administrator James Fletcher named Director Robert Gilruth to a new post, Director of Key Personnel Development, and Deputy Director Christopher Kraft to succeed him; on January 18 Kraft named Sigurd Sjoberg deputy director.
- Skylab: on January 18 the center announced crews for America's first experimental space station, then planned for launch in April 1973, for visits of 28, 56 and 56 days. Charles Conrad, Joseph Kerwin and Paul Weitz were assigned to the first, Alan Bean, Owen Garriott and Jack Lousma to the second and Gerald Carr, Edward Gibson and William Pogue to the third. The first Skylab experiment planning simulation began in late January.
Sources
- NASA, "50 Years Ago: Apollo 16 Delayed One Month, Rolls Back From the Launch Pad" (https://www.nasa.gov/history/50-years-ago-apollo-16-delayed-one-month-rolls-back-from-the-launch-pad/); the "50 Years Ago" in the original title is dropped because it goes stale; photographs of named people and a list of world events are left out; rewritten in hubnx's own words.