In spring 2026 a group of four first-year engineering students at Cal Poly Humboldt took on that problem for the Critical Agriculture Studies & Agroecology (CASA) student farm in Arcata, California, which had no pathways. They aimed for a primary route that people in wheelchairs and with other mobility devices could use, and chose a surface of crushed rock called trail mix. This summary follows their Appropedia project page.
The site
The farm sits on Foster Road, near the Arcata Bottoms, just south of downtown Arcata and a few miles from campus. The university began working the land around June 2025. It is a 26-acre plot with two acres in use as the student farm, with hopes of reaching six acres. The farm serves the CASA program as an applied learning setting, a “living laboratory” for examining the social, ecological and political dimensions of food systems.
What the path had to do
The students judged the design by five criteria, weighted 1 to 10. The path also had to be ADA compliant, last under heavy farm equipment, need no upkeep and be removable at the client’s request.
| Criterion | What it means | Weight |
|---|---|---|
| Accessibility | Wheelchair and other mobility-impaired users must be able to use it | 10 |
| Durability | Holds up to weather and use | 8 |
| Removability | Can be moved or removed if the farm’s layout changes | 8 |
| Ease of implementation | Easy to build without heavy work | 7 |
| Cost | Not too expensive to build, or to extend if it works | 6 |
Their reading found trade-offs in every material. Brick, concrete and wood are the most accessible but the hardest to remove. Sand and gravel are the opposite. Packed earth can be both accessible and removable but gets muddy, and cloth is accessible and removable but does not last. Permeability matters in rainy Humboldt, where sand and gravel drain well but are poor to walk or roll on, and designs with holes to let water through can trap crutch and cane users.
From stone tiles to trail mix
The first design used stone tiles, tested in a prototype made of wood standing in for the tiles. The first tile idea used 12 by 12 inch tiles, or 16 by 16 inch ones. The team soon found tiles far out of budget and too many work hours for the semester. They considered poured concrete, packed earth and a raised wooden path, and then, on advice from Professor Grafman, chose trail mix: pulverized rock of ¼ inch and smaller.


How the path is built
- Dig the route 6 inches deep, at least 4 feet wide to stay ADA compliant, and tamp the soil level.
- Stake a weed mat along the path, two stakes for every 10 feet plus two more to start.
- Fill to half depth with trail mix and tamp, then fill the rest and tamp again.
- Water the path with a hose to finish.
Tools are a shovel, a tamping bar, a wheelbarrow and a hose. Trail mix is sold by the yard, and one yard is 25 cubic feet.
Planned materials and cost:
| Item | Amount | Unit cost | Total |
|---|---|---|---|
| Weed barrier, 4 ft x 50 ft | 5 | USD 22.99 | USD 114.95 |
| Trail mix, one yard | 20 | USD 80.00 | USD 1,600.00 |
| Delivery fee (over 9 yards) | 1 | USD 170.00 | USD 170.00 |
| Landscape staples and stakes | 1 | USD 10.00 | USD 10.00 |
| Grand total | USD 1,894.95 |
What got done
For the engineering course the team could not go beyond digging. The work was hard, and they halted because of soil contamination. After the first day of digging they had a trench 4 feet by 10 feet by 6 inches, and after the fourth day, 4 feet by 50 feet by 6 inches.


Looking after it
The team recommends re-tamping once a year, judging by the traffic the path will get. Weed mats are the main weed control, and weeds that get through can be pulled. If gravel is lost to use or Arcata weather, fill and level the area with more and tamp it to match. A yearly check: make sure the path is flat and level, and if not, add trail mix, level it and water it. For a sinking path or a hole, add more trail mix.
Lessons and next steps
Testing showed trail mix was the only design that fit their constraints, and it handled daily farm use well. The students learned to plan for setbacks and not to get too attached to an idea before knowing it will work. If the path works as the client hopes, it could be extended to connect more of the farm.
Sources
- Appropedia, CASA Student Farm primary accessible pathway, by its contributors, licensed under CC BY-SA 4.0. Photos by Dean Bruhl on Appropedia, CC BY-SA 4.0. Changed here: rewritten in hubnx’s own words and condensed; the page’s literature review, citations, team list and currency conversions are left out.