When space shuttle Columbia rolled out to Launch Pad 39A on May 26, 1982, it set a record: just seven days in the Vehicle Assembly Building (VAB). STS-4, planned for launch on June 27, was the fourth and final mission of the Orbital Flight Test program, and its preparation showed the shuttle getting faster.



Left: The External Tank (ET) for STS-4 arrives at NASA's Kennedy Space Center (KSC) in Florida. Middle: Workers tow Columbia from the Shuttle Landing Facility to the Orbiter Processing Facility (OPF) after STS-3. Right: Ground crews in the VAB lower the ET for mating with the two Solid Rocket Boosters.
From landing to stacking
STS-3 ended on March 30, 1982, when Columbia landed at Northrup Strip at the White Sands Missile Range in New Mexico. It reached KSC atop its Shuttle Carrier Aircraft on April 6. Workers demated it the next day and towed it to the OPF, and the payloads came out of the cargo bay on April 13.
Meanwhile, in the VAB's High Bay 3, workers began stacking the Solid Rocket Booster (SRB) segments on Mobile Launch Platform-1 on March 29 and finished on April 8. On April 16 they began attaching the ET, which had been in testing in the VAB since Jan. 22, and completed the job in record time the next day.
In the OPF, engineers removed about 1,000 thermal protection system tiles. About 800 were densified and replaced, and the other 200 were replaced with new tiles. The orbiter's toilet, which had problems on STS-3, was removed, repaired and replaced. Crews installed payloads including the Induced Environment Contamination Monitor (IECM) in the cargo bay and the Continuous Flow Electrophoresis System (CFES) in the middeck. After a record-setting 42 days in the OPF, 11 fewer than for STS-3, Columbia went to the VAB, where it was mated to the ET and SRBs by May 20. A Shuttle Interface Test on May 21-25 verified the connections and onboard systems.



Left: Crews prepare to rotate Columbia to vertical. Middle: Workers lift it to High Bay 3. Right: Workers lower it for mating with the ET and SRBs.
The crew and the payloads
NASA announced Thomas K. "Ken" Mattingly and Henry W. "Hank" Hartsfield as the crew on Feb. 22, 1982, and for the first time assigned no backup crew. Managers believed they had a pool of trained astronauts to draw on, and the two had been the STS-3 backup crew.


Left: Mattingly and Hartsfield train on the Remote Manipulator System (RMS) at Johnson Space Center (JSC). Right: The crew in the Shuttle Mission Simulator.
At a May 21 press conference on their seven-day flight, the final test flight of the program, Mattingly said, "What we're building here is a bridge to the future." Hartsfield said they were trying to prepare to move into the operations era, and noted that KSC processing times had fallen with each flight.



Left: The Cryogenic Infrared Radiance Instrumentation for Shuttle (CIRRIS), the primary Department of Defense payload. Middle: The IECM in the payload bay before STS-3. Right: The CFES in the middeck before launch.
- CIRRIS: a testbed for future Department of Defense operations on the shuttle, planned to observe the Earth's limb and atmospheric background.
- IECM: flown on STS-2 and STS-3 and left in the cargo bay. The crew planned to grapple and move it with the Canadian-built RMS. At 850 pounds, it set a record as the heaviest payload the RMS had maneuvered.
- CFES: developed jointly by McDonnell Douglas Astronautics and the Ortho Pharmaceuticals division of Johnson & Johnson, to use microgravity to isolate ultrapure samples of biological materials.
- Two biomedical experiments chosen through the Space Shuttle Student Involvement Project, in which the crew planned to take part.
Thermal performance in different attitudes was also to be evaluated, continuing work from STS-3.
Rollout and countdown rehearsal
On May 26, Columbia, mated to its ET and SRBs on the platform, began the 3.5-mile trip to Pad 39A on the crawler transporter. It took about six hours.



On May 29 Mattingly and Hartsfield took part in the Countdown Demonstration Test, a dress rehearsal of launch day with no fuel in the ET. A computer problem delayed it by more than four hours, but it concluded successfully just before simulated main engine ignition.


Left: The crew leaves the Operations and Checkout Building for the transfer van. Right: After the test, the crew answers reporters' questions at the pad.
On June 2 crews filled the ET with liquid oxygen and liquid hydrogen in a cryogenic fuel loading test. On June 1 at JSC, controllers led by Lead Flight Director Charles R. "Chuck" Lewis began a 57-hour simulation of STS-4 with the crew in the shuttle mission simulator. At KSC the countdown preparation cycle began on June 15 and the final countdown on June 23.
Sources
- NASA History, "40 Years Ago: Columbia Rolls out to its Launch Pad in Preparation for STS-4", https://www.nasa.gov/history/40-years-ago-columbia-rolls-out-to-its-launch-pad-in-preparation-for-sts-4/; rewritten in hubnx's own words.