Space shuttle Columbia needed fewer days in each processing facility, and far fewer replacement heat shield tiles, for its third flight than for its first. In February 1982, NASA was preparing it for STS-3, planned for launch on March 22: closing its payload bay doors, towing it to the Vehicle Assembly Building (VAB), joining it with its external tank and solid rocket boosters, and rolling the stack out to Launch Pad 39A at Kennedy Space Center (KSC) in Florida. Astronauts Jack R. Lousma and C. Gordon Fullerton took part in a countdown demonstration and an emergency escape drill at the pad, and at Johnson Space Center (JSC) in Houston they ran a long simulation of their flight with mission controllers.

Workers at NASA’s Kennedy Space Center in Florida roll space shuttle Columbia out of the Orbiter Processing Facility for the rollover to the Vehicle Assembly Building (VAB).
Stacking
In late January 1982, after installing the mission’s payloads, workers in KSC’s Orbiter Processing Facility (OPF) closed Columbia’s payload bay doors. On Feb. 3 they backed the orbiter out and towed it to the VAB, where they mated it with the external tank and the twin solid rocket boosters, which had been stacked beforehand on a mobile launch platform. Engineers began testing the integrated vehicle, and Lousma and Fullerton took part in the vehicle integrated test on Feb. 12 from Columbia’s flight deck.

In the VAB, workers lift Columbia to mate it with its external tank and solid rocket boosters.
Rollout
In the predawn hours of Feb. 16, the crawler transporter carrying Columbia on its mobile launch platform began the slow trip from the VAB to Launch Pad 39A, 3.5 miles away. Six hours later the stack reached the pad, and workers began interface tests with the launch tower.

Space Shuttle Columbia exits the Vehicle Assembly Building at the start of the rollout to Launch Pad 39A.

Nearly there – Columbia approaches its final position on Launch Pad 39A.
The lessons from the turnaround between STS-1 and STS-2 produced a shorter, better turnaround for the third mission. Columbia spent 103 days in the OPF after STS-1 but only 47 days after the second mission, and 21 days in the VAB after the first mission but only 11 after STS-2. Only 449 heat shield tiles needed replacing after the second mission, compared with 1,872 after the first.
Countdown demonstration and fuel test
Three days after the rollout, Lousma and Fullerton took part in the final two hours of a 33-hour countdown demonstration test. They put on their pressure suits, rode out to the pad and climbed aboard Columbia as on launch day, although no fuel was loaded in the external tank. The practice countdown ran down to the time of space shuttle main engine ignition. Afterward they were instructed in the pad's emergency escape system, including the slide wire basket.

STS-3 astronauts C. Gordon Fullerton, left, and Jack R. Lousma arrive at Launch Pad 39A for the countdown demonstration test.
The last major test of the shuttle system, the cryogenic load, filled the external tank with super-cold liquid hydrogen and liquid oxygen. Engineers completed it successfully on Feb. 25.

Space Shuttle Columbia on Launch Pad 39A during the cryogenic fuel loading test.
Training in Houston
At JSC, Lousma and Fullerton took part in a 57-hour simulation of their mission that ended on Feb. 5. With the backup crew of Thomas K. “TK” Mattingly and Henry W. “Hank” Hartsfield, they worked from the shuttle mission simulator in Building 5 while flight controllers were on console in the Mission Control Center in Building 30. The simulation included many of the robotic operations with the cargo bay payloads. On Feb. 26 the crew met the press. They also introduced the Insects in Flight Motion Study, an experiment designed by a high school senior chosen for the Shuttle Student Involvement Project for Secondary Schools, a joint program of NASA and the National Science Teachers Association. Flown on STS-3, it was meant to study the flying behavior of velvetbean caterpillar moths and honeybee drones in weightlessness.
Sources
- NASA, Columbia Rolls out to its Launch Pad in Preparation for STS-3, NASA History; rewritten in hubnx's own words.