By early 1969, after the success of the Apollo 8 flight around the Moon, NASA believed a landing by summer was possible. This NASA history post covers February 1969, five months before Apollo 11, when three crews and their backups trained for the next three missions while workers at Kennedy Space Center prepared the rockets. Apollo 9 would test the Lunar Module (LM) in Earth orbit in early March, Apollo 10 in May would be a lunar-orbit dress rehearsal for the landing, and Apollo 11, planned for July, would be the landing itself.
Apollo 8’s crew goes on tour
Frank Borman, his wife Susan and their two sons left on Feb. 2 on a presidential Air Force jet for a European goodwill tour, as President Richard M. Nixon had announced on Jan. 30. His Apollo 8 crewmates James A. Lovell and William A. Anders stayed home because they had begun training as part of the Apollo 11 backup crew. The 19-day tour visited London, Paris, Brussels, Den Haag, Bonn, West Berlin, Rome, Madrid and Lisbon. The family met royalty, politicians, scientists and Pope Paul VI, and Borman gave lectures narrating a film from his flight and held many press conferences.
Apollo 9: countdown trouble
Apollo 9’s crew, James A. McDivitt, David R. Scott and Russell L. Schweickart, planned the first crewed test of the LM during a 10-day Earth-orbit mission. They and their backups spent many hours in simulators and training for the spacewalk, the only one planned before the landing mission. It would test the spacesuit and its Portable Life Support System and show that a crew could transfer outside if the internal tunnel or hatches failed. The crew briefed reporters on Feb. 8.
Senior NASA managers held the Flight Readiness Review at Kennedy in the first week of February and set the launch for Feb. 28. The next week, engineers in Launch Control Center Firing Room 2 ran the Countdown Demonstration Test, a dress rehearsal, and on Feb. 12 the crew took part in its last two hours in their suits aboard the spacecraft. The real countdown began Feb. 26 but halted the next day because the astronauts had developed head colds. Managers reset the launch for March 3, and the countdown restarted on March 1.

Image from NASA’s page.

Image from NASA’s page: Associate Administrator George E. Mueller, Apollo Program Director Samuel C. Phillips, KSC Director Kurt H. Debus, Manned Spacecraft Center Director Robert R. Gilruth and Marshall Space Flight Center Director Wernher von Braun.
Apollo 10: stacked and waiting
With Apollo 9 on Pad 39A, workers finished stacking the Apollo 10 vehicle in the Vehicle Assembly Building (VAB). The spacecraft arrived from the Manned Spacecraft Operations Building on Feb. 6 and was stacked the same day, and integrated tests began ahead of a rollout to Pad 39B in mid-March. Its crew, Thomas P. Stafford, John W. Young and Eugene A. Cernan, and their backups, spent much of the month in simulators and testing their suits in vacuum chambers.

Image from NASA’s page.
Apollo 11: training for the surface
The prime crew, Neil A. Armstrong, Michael Collins and Edwin “Buzz” Aldrin, and their backups, James A. Lovell, William A. Anders and Fred W. Haise, trained for the landing. The aim was to show that the spacecraft could land two astronauts and bring them back safely, but the surface work also covered collecting samples and deploying experiments. In a planned excursion of two and a half hours, Armstrong and Aldrin were to set up the three instruments of the Early Apollo Surface Experiment Package: a passive seismometer, a laser ranging retro-reflector and a solar wind composition experiment. On Jan. 21 geologist-astronaut Harrison H. “Jack” Schmitt and Don L. Lind rehearsed the deployment while Aldrin watched.
On Feb. 24 Armstrong, Aldrin, Lovell and Haise took their only geology field trip, near Sierra Blanca, Texas, about 90 miles southeast of El Paso, practicing sampling a representative collection of rocks, a skill needed to pick the best samples in a short moonwalk. Geology teaching had been part of astronaut training since 1964.

Image from NASA’s page.
The Apollo 11 Saturn V’s three stages had all reached the VAB by mid-February, and the first stage was stacked on Feb. 21. In the nearby MSOB, engineers tested docking between the Command Module and LM on Feb. 10 and mated the LM’s ascent and descent stages five days later. The Lunar Landing Training Vehicle was still grounded after its December 1968 crash, so the Lunar Landing Research Facility at Langley was the only high-fidelity trainer for the descent, and Armstrong practiced landings there on Feb. 12.

Image from NASA’s page.
Keeping Moon germs in
To prevent any lunar microorganisms from contaminating Earth, NASA built the 83,000-square-foot Lunar Receiving Laboratory at the Manned Spacecraft Center, designed to isolate the astronauts, their spacecraft and the samples while keeping the samples pristine. The Mobile Quarantine Facility would isolate returning astronauts from just after splashdown until they reached the laboratory. On Feb. 6 workers placed it in a vacuum chamber to test its emergency oxygen supply during a simulated aircraft pressure loss, and three test subjects completed the test successfully.
Sources
- NASA, 55 Years Ago: Five Months Until the Moon Landing; rewritten in hubnx’s own words.