About an hour after liftoff, when JPSS-1 separated from the upper stage of its Delta II rocket and its solar array deployed, the launch of NOAA's newest polar-orbiting satellite was declared a success. The job was not done. The satellite, now known as NOAA-20, would not be declared operational for several months. In the meantime it was checked out by engineers and scientists from NASA, NOAA and the Joint Polar Satellite System's industry partners, Ball Aerospace, Raytheon, Northrop Grumman and Harris, who test everything from communications to science instruments.

Image from NOAA's page.
The checkout phase
The phase, also called "post-launch testing," began Saturday, November 18, 2017, the moment the satellite separated from the Delta II. A Mission Operations Support Team of about 50 engineers runs a round-the-clock plan to evaluate nearly every piece of hardware, until the satellite is ready for handover to NOAA for routine operations.
There are four sub-phases: spacecraft commissioning, outgassing, instrument activation and characterization, and operational science testing. They do not run one after another. Tests from different sub-phases often overlap, and orbit raising usually goes on alongside the early ones.
1. Commissioning the spacecraft
This tests the primary systems. Tom Wrublewski of the JPSS program named the key ones: the power system, with a solar array that must deploy right after launch to recharge the batteries; the attitude control system, which keeps the satellite pointing at Earth; the communication system, with antennas and transmitters sending housekeeping data to operators and mission data to ground stations; and the computer and data system that monitors and controls the craft. The propulsion system is checked too, since it is used for orbit raising, station keeping and, at the end of the mission, safely de-orbiting the satellite into the ocean.
2. Activating and outgassing the instruments

Image from NOAA's page: NOAA-20's Advanced Technology Microwave Sounder, the first instrument turned on and the first to return science data.
Engineers switch the instruments on to confirm they work, then wait through an outgassing period before opening the doors that protect their sensors. During outgassing, chemical residues and water vapor from the materials used on the satellite and instruments evaporate into the vacuum of space. Wrublewski noted that keeping things clean on the ground is hard: the multi-layer insulation blankets protecting the instruments hold water vapor, which heaters and vacuum drive off. Instruments with sensitive optics, such as VIIRS, CrIS, CERES and OMPS, get the early weeks of checkout to let contaminants migrate away.
3. Characterization, calibration and validation

Image from NOAA's page: fires near Santa Barbara, California, made with data from NOAA-20's Visible Infrared Imaging Radiometer Suite.
Next engineers check whether the instruments perform as they did in pre-launch tests and as the instruments on the predecessor, the NOAA-NASA Suomi NPP satellite, do, making sure they survived launch with no surprises. Some tests use maneuvers: rolls (side to side), yaws (twisting left and right) and a pitch, or "back flip," turning the satellite 180 degrees. They help engineers understand how the instruments interact with the spacecraft and how the space environment, such as the light reaching a sensor, affects them.
4. Operational science testing
This inspects the quality of the data. Bryan Fafaul, project manager of the JPSS Flight Project, described it as making sure the instrument data sent through the ground system are what they are supposed to be.
When things do not behave
Fafaul said you should expect to learn things after launch, because a satellite cannot be tested exactly as it will behave in space, and anomalies will occur. An anomaly does not necessarily mean a problem, but it has to be understood. The JPSS Mission Systems Manager assembles an anomaly response team of NOAA, NASA and industry experts to discuss it and plan a response. Once it is resolved it is documented extensively so future operators know what to do if it recurs.

Image from NOAA's page: JPSS-1 (NOAA-20) during pre-launch testing.
Handover
At the time of the post the phase was expected to end in mid-February. Vanessa Griffin, director of NOAA's Office of Satellite and Product Operations (OSPO), and her deputies were to meet NASA's team and review a checklist covering instrument performance, documentation and manuals, procedure updates and operator training. If everything is met, NASA hands operations to OSPO, which manages the ingestion, processing and distribution of NOAA satellite data and products to users at home and abroad.
Raising the orbit
The rocket put NOAA-20 into an "insertion orbit," about 10 kilometers lower than its operational orbit. The satellite has to be placed precisely 50 minutes apart from Suomi NPP, its polar-orbiting partner. Engineers do this with five burns of the propulsion system.
| Burns | Purpose |
|---|---|
| First and second, up to 30 seconds each | Thruster checkouts, and adjusting elements of the orbit |
| Third | Adjusts the inclination, the angle between the orbital plane and the equator |
| Fourth and fifth | Reach a "frozen" orbit, in which the satellite's altitude stays constant at the same point in each orbit over a long period, while keeping the 50-minute separation from Suomi NPP |
How long it takes varies. For NOAA-20, orbit raising took about three weeks and was done in January 2018, and one more small maneuver was planned before handover.
Sources
- NOAA National Environmental Satellite, Data, and Information Service (NESDIS), "From Launch to Operational: An Overview of NOAA-20's Checkout Phase": https://www.nesdis.noaa.gov/news/launch-operational-overview-of-noaa-20s-checkout-phase; rewritten in hubnx's own words. The animations the source embeds are left out; the people quoted are paraphrased.