A vacuum chamber 30.5 meters (100 feet) across and 37.2 meters (122 feet) tall was built to test nuclear space hardware, yet in all its history it has tested only non-nuclear hardware. It is the heart of NASA's Space Environments Complex (SEC) at the Neil Armstrong Test Facility (formerly Plum Brook Station) in Sandusky, Ohio, operated by NASA Glenn Research Center. The complex houses the largest and most powerful space-environment simulation facilities in the world, and government, academic and private-sector users can book them.

Space Environments Complex, aerial view (NASA).
The four test capabilities
| Facility | What makes it notable |
|---|---|
| Space Simulation Vacuum Chamber (Space Power Facility) | The largest vacuum chamber in the world, 22,653 cubic meters in volume, made to test hardware in a simulated low-Earth-orbit environment |
| Reverberant Acoustic Test Facility | The most powerful acoustic test chamber in the world: 14.5 by 11.4 by 17.4 meters, with 36 horns and 36 modulators and a frequency range of 25 to 10,000 Hz |
| Mechanical Vibration Facility | The most powerful spacecraft shaker system in the world: a six-degree-of-freedom table on a reaction mass of 2.1 million kilograms, for payloads up to 34,000 kilograms, shaking at 5 to 150 Hz |
| EMI/EMC Test Facility | The world's largest reverberant chamber for electromagnetic interference and compatibility, using the vacuum chamber's structure; used in 2020 to test the Artemis I Crew Service Module |
How the vacuum chamber works
The chamber sustains high vacuum and makes cold environments with a cryogenic shroud that reaches -160°C (-250°F). It can simulate solar and thermal radiation and gives a high degree of vibration isolation. It is made of aluminum and surrounded by a concrete enclosure 1.83 to 2.44 meters thick, with two 15.24-meter-square entrances 180 degrees apart that open into high bays, and an 18-tonne vacuum-compatible polar crane at the top. A removable, reconfigurable cryoshroud provides a thermal background of -160°C to 80°C within an envelope about 12 meters across and high. Up to 7 megawatts of power is available for the lamps, heater panels and infrared heaters that simulate heat. The roughing pumps, cryopumps and turbopumps bring the chamber down from atmospheric pressure in stages: about 2 hours to 20 Torr, 3 hours more to 1×10⁻² Torr and 2 hours more to 4×10⁻⁶ Torr.

Wide-angle view into the test chamber (NASA).
A history of tests
The complex was built in 1969 for nuclear and non-nuclear testing of large space systems for missions beyond low Earth orbit, with extra capacity, such as huge high bays and doors, to take on more demanding tests later. The vacuum chamber, a $28.4 million facility, was never used for the nuclear-power tests it was designed for.
- Brayton power system. The first test was of a 15- to 20-kilowatt Brayton Cycle Power System for space, which converted solar thermal energy to electricity with a closed loop using a helium-xenon gas mixture. Three methods of simulating solar heat were used, and the system underwent simulated orbits with 62 minutes of sun and 34 minutes of shade.
- Viking's rocket shroud. In the late 1960s NASA planned the Viking missions to Mars, whose landers were the heaviest payloads ever tried on a Centaur upper stage, so engineers paired it with a Titan III booster and a new Lockheed-designed Centaur Standard Shroud. Tests ran at Plum Brook in 1973 and 1974, and the shroud performed flawlessly in the 1975 Viking launches.
- Mars Pathfinder and the space station. Airbag performance testing for Mars Pathfinder took place in 1995, and the International Space Station's heat rejection radiator was developed here from 1996 to 1999.
- Orion and Artemis. An ogive panel that protects Orion's crew module from launch and abort noise was blasted with 161 dB in the acoustic chamber. The Orion Environmental Test Article returned to Armstrong in January 2024 for an 11-month test campaign needed for the safety and success of Artemis II, and in November 2024 it completed the Forward Bay Cover jettison test, the last piece that must eject before the parachutes deploy.
- Dream Chaser. In February 2024 NASA used the shaker table to expose Sierra Space's Dream Chaser spaceplane, stacked on its Shooting Star cargo module, to vibrations like those of launch and re-entry.

The Orion Crew Module's setup just before the Forward Bay Cover deployment test (NASA).

Setup of a Brayton Cycle Power System test in the Space Power Facility's vacuum chamber (NASA).
Sources
- NASA, Space Environments Complex; rewritten in hubnx's own words.