Power plants must report their total emissions, but the measurements behind those reports can be uncertain by 10% to 20% for carbon dioxide at a typical U.S. coal-fired plant, leaving actual totals, in NIST’s phrase, up in the air. To tighten that, NIST built an unusual precision-measurement facility on its Gaithersburg, Maryland campus: a 50 meter horizontal smokestack. Its aim is to find a way to measure CO2 flux with 1% uncertainty at reasonable cost. This summary follows a 2014 NIST news article written while the facility was nearly finished.

Diagram illustrating numerous measurement challenges in determining smokestack flow at coal-fired power plants. NIST.
Why it matters
On June 2, 2014 the Environmental Protection Agency announced draft plans to cut greenhouse gas emissions from power plants by as much as 30% by 2030. Electricity generation accounts for about 38% of U.S. CO2 emissions, more than any other sector, and the country has more than 500 coal-fired power plants, from a few megawatts to 2,000 MW or more. By the EPA’s figures, their average emission rates are 2,249 pounds of CO2, 13 pounds of sulfur dioxide and 6 pounds of nitrogen oxides per megawatt-hour.
James Whetstone, head of NIST’s Greenhouse Gas Measurements program, which funds the project, says plants must report totals but need not estimate the uncertainty of their measurements, so the quality of the reported data is hard to judge. Better measurement of total flow would improve measurements of other pollutants too, such as sulfur compounds and nitrous oxide.
Why smokestack flow is hard to measure
Each stack has a Continuous Emission Monitoring System (CEMS). About two-thirds of them are ultrasonic: two transmitter/receiver units at different heights send a sound signal between them, which travels faster with the flow than against it. The transit-time difference over that one path gives the gas velocity, and multiplying by the stack’s area gives the flow volume.
But flow in a stack is turbulent and uneven, partly because the gas makes a sharp 90-degree turn from the scrubber into the stack. Swirl adds a sideways component to the velocity and introduces error; asymmetric and rotating flows are bad for accurate measurement. Some stacks are 10 meters across. Adding more pairs of ultrasonic units that cover different paths is likely to help, and one goal of the project is to learn how much multi-path metering gains.
A second goal is calibration. The EPA requires CEMS to be calibrated periodically against velocity readings from two pitot tubes, pressure probes placed facing into the flow through side ports. NIST’s Aaron Johnson says no one knows how to put uncertainties on those readings: pitot tubes differ, practitioners differ and there is no traceability to the SI unit of flow, cubic meters per second. Putting a pitot tube in the flow changes what it measures, and the smaller the cross-section the larger that blockage effect. It is usually negligible in a big stack but arises when probes are calibrated in small apparatus, and it is poorly understood.
The simulator
The scale-model stack differs from a real one. It is horizontal rather than vertical, it moves air rather than combustion gas, and its pipes are about 1 meter across rather than about 10. Air is a reliable stand-in because modern coal plants use wet scrubbers, so the exhaust is not much warmer than the surroundings, buoyancy is negligible and large fans force the gas up the stack.
- Reference section. Fans draw air in through a bell-shaped port into a channel 0.9 m across holding an 8-path ultrasonic flow meter traceable to NIST primary flow standards, with an expanded uncertainty of 0.5% at 95% confidence. Air speed here ranges from 11 to 44 meters per second under near-ideal flow, symmetric and without swirl.
- Test section. The air turns 90 degrees into a pipe 1.2 m across, where speed runs from 6 to 25 m/s, a range common in power-plant stacks. Different “de-conditioning plates” create controlled asymmetric flow profiles, and a special segment can be fitted with pitot tubes and a multi-path ultrasonic test fixture.

Diagram of the planned facility. NIST.
Results will be compared with computational fluid dynamics (CFD) calculations. Jacob Ricker says this lets the team scale up from a four-foot test section to the thirty-foot sections of real stacks, validate the computer models and predict the measurement uncertainty of a real stack without building a full-sized one. NIST’s Dimensional Metrology Group is designing a way to measure transducer positions and orientation inside the pipes with laser-tracker coordinate-measuring machines; two of its members completed a preliminary measurement of one pipe section. The facility will also test other approaches: tracers in the flow, long-wavelength acoustics and LIDAR.
John Wright, a project leader in the Fluid Metrology Group, says the simulator has drawn interest from researchers in other countries, including China, and a workshop is being planned. The goal is to improve stack flow measurements and put solid uncertainty analyses behind them so that decisions rest on reliable data.