JPSS-1, now NOAA-20, lifted off from Vandenberg Air Force Base on November 18, 2017, and the launch was judged a success about an hour later, when the satellite separated from the Delta II upper stage and its solar array deployed. Not quite mission accomplished: the satellite then went through a checkout phase, which concluded in mid-February 2018.

Image from NOAA's page: the JPSS-1 (NOAA-20) launch.
What the checkout covered
Scores of engineers and scientists from NASA, NOAA and the Joint Polar Satellite System's industry partners, Ball Aerospace, Raytheon, Northrop Grumman and Harris, tested everything from communications to science instruments, round the clock. The work falls in four phases that often overlap: commissioning the spacecraft, outgassing, activating and characterizing the instruments, and operational science testing.
- Commissioning tests the primary systems. Tom Wrublewski of the JPSS program named them as power, attitude control, communications and the computer and data system, plus propulsion, which is needed for orbit raising, station keeping and the safe de-orbit at the end of the mission.
- Activation and outgassing. Engineers turn instruments on, then wait while residues and water vapor trapped in materials and insulation blankets evaporate into the vacuum, before opening the sensor doors. The Advanced Technology Microwave Sounder was the first instrument on and the first to send back science data. NOAA-20's VIIRS instrument produced an image of the December 2017 wildfires in Santa Barbara, California, in the course of this work.

Image from NOAA's page: the December 2017 wildfires in Santa Barbara, made with data from NOAA-20's VIIRS instrument.
- Calibration and testing. Engineers compare instrument performance with pre-launch tests and with the predecessor, Suomi NPP, using maneuvers such as rolls, yaws and a 180-degree pitch, or "back flip." Then comes operational science testing, which Bryan Fafaul of the JPSS Flight Project described as making sure the data coming through the ground system are what they should be.
Anomalies are expected, Fafaul said, because a satellite cannot be fully tested for space on the ground. When one appears, an anomaly response team of NOAA, NASA and industry personnel is assembled to plan a response, and the result is documented extensively for the future operators.
The handover
The checkout concluded in mid-February 2018. Vanessa Griffin, director of NOAA's Office of Satellite and Product Operations (OSPO), and her deputies met members of the JPSS program and NASA's Mission Operations Support Team to confirm that all requirements had been met, including training of operations personnel. After NOAA completed its final checklist, NASA officially handed command and control of NOAA-20 to OSPO, which handles the ingestion, processing and distribution of NOAA satellite data and products for users at home and abroad.
Not operational yet
The article is careful about the next step. Finishing checkout does not make the satellite operational. NOAA still had to validate all of its data products before the National Weather Service could use them. Only then would NOAA-20 be declared operational as NOAA's primary polar-orbiting weather satellite, and NOAA promised an announcement over the following weeks.
Sources
- NOAA National Environmental Satellite, Data, and Information Service (NESDIS), "From Launch to Operations: What Happens During NOAA-20's Checkout Phase": https://www.nesdis.noaa.gov/news/launch-operations-what-happens-during-noaa-20s-checkout-phase; rewritten in hubnx's own words. People quoted are paraphrased.