If NASA's Launch Services Program (LSP) at Kennedy Space Center had a magic number for 2018, it was six: six primary NASA missions, from two coasts, within about six months, on six rocket configurations (five different rockets). The program's deputy manager said it had not had such a dense and diverse manifest since 2003. This is a look back at the plan as NASA described it, with launch dates as scheduled at the time.

The Launch Services Program's six mission patches. Image from NASA's page.
The plan
| Mission | Scheduled date | Rocket and site |
|---|---|---|
| NOAA's GOES-S weather satellite | March 1 | United Launch Alliance (ULA) Atlas V, Cape Canaveral Air Force Station |
| Transiting Exoplanet Survey Satellite (TESS) | March 20 | SpaceX Falcon 9, Cape Canaveral |
| InSight Mars lander | May 5 | ULA Atlas V, Vandenberg Air Force Base, California |
| Parker Solar Probe | July 31 | ULA Delta IV Heavy, Cape Canaveral |
| Ice, Cloud, and land Elevation Satellite-2 (ICESat-2) | September 12 | ULA Delta II, Vandenberg |
| Ionospheric Connection Explorer (ICON) | later in the year | Orbital ATK Pegasus XL, carried by the L-1011 Stargazer aircraft |

In a clean room in Titusville, Florida, on January 16, 2018, technicians and engineers prepare GOES-S for encapsulation in its payload fairing. NASA photo.
What each mission was for
- GOES-S was to be renamed GOES-17 once in geostationary orbit, joining GOES-R (now GOES-16), launched just over a year earlier, to give the big picture of weather, including precise data on hurricanes.
- TESS was to search for planets outside the solar system, including ones that could support life.
- InSight was the first of two interplanetary missions and the first ever launched from the West Coast. A NASA Discovery Program mission, its single lander would use seismic sensors to study the interior of Mars.
- Parker Solar Probe, about the size of a small car, would come within about 4 million miles of the Sun's surface to study its corona. It would be the first Delta IV Heavy to fly a science payload, with a launch window of just 20 days.
- ICESat-2 would carry one instrument, ATLAS, to gauge the slope of Earth's surface and estimate the annual height change of the Greenland and Antarctic ice sheets to within 4 millimeters, the width of a pencil. It would fly on the final Delta II.
- ICON would study the zone high in the atmosphere where Earth's weather meets space weather. Pegasus is the only airborne-launched rocket: released at 39,000 feet.

TESS in a conceptual illustration. NASA's Goddard Space Flight Center.

InSight being prepared for vibration testing at Lockheed Martin Space in Denver. NASA/JPL-Caltech/Lockheed Martin.
Why planetary windows are hard
A launch director said interplanetary missions are harder, because their trajectories allow launch only in precise windows. To reach Mars in 2018, the program had about 4.5 weeks, from early May to the first week of June, or it would have to stand down for about 26 months. The same director said the last Delta II launch would hold a special place for people who had worked on that rocket.

A ULA Delta IV Heavy common booster core for the Parker Solar Probe arrives at Cape Canaveral for preflight processing. NASA photo.

Engineers and technicians check the fit of ICESat-2's telescope to its sling at NASA's Goddard Space Flight Center in Greenbelt, Maryland. NASA photo.

NASA's ICON mission, in an artist's concept, studies the ionosphere from a height of about 350 miles. NASA Goddard's Conceptual Image Lab.
Sources
- NASA, "2018: A Big Year for NASA's Launch Services Program" (https://www.nasa.gov/centers-and-facilities/2018-a-big-year-for-nasas-launch-services-program/), a preview whose dates are as scheduled at the time; quotations from program officials are paraphrased and unnamed; rewritten in hubnx's own words.