When Columbia came home from the first shuttle flight, it needed to be readied for a flight that would carry the first shuttle science experiments and test the Canadian-built robotic arm for the first time in space. By August 1981 the work at NASA's Kennedy Space Center (KSC) in Florida had reached stacking and rollout.
Rebuilding the orbiter and the stack
After STS-1, with astronauts John W. Young and Robert L. Crippen, Columbia returned to KSC on April 28, 1981. The external tank (ET) for STS-2 had arrived on April 22 for inspection and checkout. Workers finished assembling the twin solid rocket boosters (SRBs) on the mobile launch platform in early June and mated the ET to them on June 30. In the Orbiter Processing Facility, technicians replaced about 1,300 tiles of the thermal protection system. On June 29 workers installed the Spacelab pallet carrying the five experiments of the Office of Space and Terrestrial Applications-1 (OSTA-1) payload, and the Canadian-built remote manipulator system (RMS), in the payload bay. On July 29, engineers finished a two-day Orbiter Integrated Test to verify that the software and hardware in Columbia and its payloads were compatible.
| Date in 1981 | Step |
|---|---|
| April 22 | External tank arrives |
| April 28 | Columbia returns to KSC |
| June 29 | OSTA-1 pallet and robotic arm installed |
| June 30 | Tank mated with boosters |
| August 10 | Columbia towed to the Vehicle Assembly Building (VAB) |
| August 26 | Nine-day Shuttle Interface Test completed |
| August 31 | Rollout to Launch Pad 39A |
The crew speaks
On August 3 at the Johnson Space Center in Houston, prime crew members Joe H. Engle and Richard H. Truly held their preflight press conference. They described a planned mission of five days and six hours, then targeted for a September 30 launch, and the main tasks: testing the arm's mobility and grasping, operating the OSTA-1 experiments, and continuing engineering tests of the new vehicle. Engle said they would be ready when the vehicle was. Truly said the mission rules were very conservative and that coming home early under them would still count as a successful flight. Mission planners put the more critical tests in the first two days.

Astronauts Richard H. Truly and Joe H. Engle at the preflight press conference (NASA).
Stacking in the VAB
Before dawn on August 10, ground crews towed Columbia the short distance from the processing facility to the VAB. There workers lifted it six inches off the ground to retract the landing gear, tilted it vertical and raised it 190 feet in the air before lowering it onto the tank and boosters on the mobile launch platform. On August 26, engineers completed the nine-day Shuttle Interface Test to check the mechanical and electrical connections among orbiter, tank and boosters and the working of the flight systems. The prime crew and the backups, Thomas K. Mattingly and Henry W. "Hank" Hartsfield, took part with simulated countdowns, two simulated ascents (a normal one and a Return-to-Launch-Site abort) and one entry and landing. All tests succeeded, but accumulated delays pushed the target launch date to October 2.

Engle and Truly in the VAB preparing for the interface tests (NASA).
Out to the pad
At 4:45 a.m. on August 31, Columbia began its rollout to Launch Pad 39A, covering the 3.5 miles in a little more than 7 hours. Managers then aimed for a countdown demonstration test in mid-September and a launch on October 9.

Columbia leaves the VAB for the seven-hour trek to the pad (NASA).
STS-2 was the first shuttle flight to carry science experiments and the first to use the robotic arm.
Sources
- NASA, 40 Years Ago: Preparations for STS-2, Columbia's Return to Space, NASA History; rewritten in hubnx's own words.