Space shuttle Columbia was supposed to fly its second mission on October 9, 1981. A countdown rehearsal, a fuel tank test and a chemical spill on the orbiter's nose decided otherwise. A NASA history page follows the weeks after Columbia reached Launch Pad 39A on August 31, 1981.

Columbia on Launch Pad 39A at NASA's Kennedy Space Center in Florida. Image from NASA's page.
Rehearsals
After the rollout, the program targeted October 9 for STS-2, the second flight of the reusable spacecraft. The day Columbia reached its pad, controllers at Johnson Space Center in Houston began the second and final long-duration simulation of the mission, a three-day rehearsal of its first 56 hours. At Kennedy Space Center, technicians ran the Pad Validation Test to confirm the shuttle's configuration had not changed during rollout and to verify the connections between pad, vehicle and mobile launch platform.
On September 2, backup astronauts Thomas K. "TK" Mattingly and Henry W. "Hank" Hartsfield trained for emergency escape at the pad. They saw a demonstration of the slide wire system and drove the armored personnel carriers that would take the crew away from a pad emergency.

STS-2 backup astronauts Hartsfield and Mattingly during emergency egress training at Launch Pad 39A. Image from NASA's page.
On September 9, launch teams in Firing Room 1 of the Launch Control Center ran a "dry" countdown demonstration test, one in which the external tank was not filled with cryogenic propellants. STS-2 astronauts Joe H. Engle and Richard H. Truly took part in the last few hours as they would on launch day, putting on their pressure suits and climbing into Columbia's cockpit. The test ended with a simulated main engine ignition.

Truly and Engle suiting up for the countdown demonstration test. Image from NASA's page.

Truly and Engle leaving the White Room at Launch Pad 39A after the test. Image from NASA's page.
On September 15, engineers loaded the external tank with supercold liquid hydrogen and liquid oxygen. The foam insulation was not damaged, an improvement over the aftermath of a similar test before STS-1.
The spill
On September 22, while the starboard forward reaction control system was being fueled, about three gallons of highly corrosive nitrogen tetroxide oxidizer spilled onto the outside of Columbia's nose. It seeped between the heat shield tiles and essentially melted the glue holding them in place. About 360 tiles fell off or had to be removed so the area could be cleaned of residual oxidizer. Removing the oxidizer and reattaching new tiles pushed the planned launch date back to November 4.

Missing thermal protection system tiles after a spill of nitrogen tetroxide during fueling of the forward reaction control system. Image from NASA's page.
The page ends there, with "to be continued" for the next installment.
Sources
- NASA History, "40 Years Ago: Preparations Continue for Columbia's Return to Space on STS-2" (https://www.nasa.gov/history/40-years-ago-preparations-continue-for-columbias-return-to-space-on-sts-2/), a work of the United States government. The page's list of other world events in September 1981 is left out.