Автора пока нетВзять себе
- Лицензия
- CC0 1.0 (общественное достояние)По материалам www.nasa.gov
- Языки
- English
- Темы
- Наука
The new year of 1981 opened with optimism about the first launch of the Space Shuttle Program. Workers had rolled space shuttle Columbia to its seaside launch pad on December 29, 1980, and engineers began testing the entire system to prepare it for STS-1, the program's first mission. A readiness review on January 30 set February 17 for the Flight Readiness Firing (FRF) and gave an estimated launch date of April 5.
The engines pass their last big test
On January 17, the Space Shuttle Main Engines passed their final critical test at NASA's National Space Testing Laboratories in Bay St. Louis, Mississippi. It was the 12th static firing of the Main Propulsion Test Article, which had three flight-like engines, an aft shuttle fuselage and a full-size external tank. All three engines ignited as planned. As planned, engine number 3 shut down after 235 seconds while the other two kept firing for 624.5 seconds, the longest firing in the test program. All major objectives were met, including gimbaling of the engines and a full-duration run with flight nozzles. The test cleared the three engines installed on Columbia for the FRF in mid-February at Kennedy Space Center's Launch Pad 39A, a key milestone before the orbiter's first launch.
Work on the pad
At the pad, a series of validation tests, completed on January 5, verified all the interfaces between the launch pad and the vehicle. A weeklong "plugs-out" test began on January 10 and included a mock countdown to check the orbiter and ground systems; the backup crew, Joe H. Engle and Richard H. Truly, took part in its later stages, seated in Columbia's cockpit. Between January 22 and 24, engineers filled and emptied the large external tank with cryogenic propellants: 384,000 gallons of liquid hydrogen and 140,000 gallons of liquid oxygen.

Space shuttle Columbia on Launch Pad 39A. Image from NASA's page.
A rehearsal in Mission Control
Flight controllers in the Mission Control Center at NASA's Johnson Space Center in Houston completed the sixth and second to last full-duration, 54-hour simulation of the STS-1 mission on January 20-22. Three teams of controllers, led by three flight directors, followed the STS-1 flight plan while the simulation team introduced simulated anomalies. The prime crew, John W. Young and Robert L. Crippen, took part from the fixed-base Shuttle Mission Simulator at Johnson and responded successfully to all the anomalies presented.
On January 23, Young and Crippen held a press conference at Johnson to outline their 54-hour mission and what remained before launch: one more full-mission-duration simulation after the FRF, and the terminal countdown demonstration test about two weeks before launch.

NASA astronauts John W. Young, left, and Robert L. Crippen, the prime crew for STS-1, in a lighthearted moment during a preflight press conference at Johnson Space Center in Houston. Image from NASA's page.

Crippen, left, and Young pose for photographers with a model of space shuttle Columbia after the press conference. Image from NASA's page.
A change at the top of NASA
During the presidential transition, outgoing President Jimmy Carter and incoming President Ronald Reagan agreed to name NASA Deputy Administrator Alan M. Lovelace acting administrator, effective January 20, 1981, the day of Reagan's inauguration. In October 1980, Administrator Robert A. Frosch had told Carter he was resigning effective that same day. Lovelace served as acting administrator until the Senate confirmed Reagan's choice, James M. Beggs, on July 10, 1981.
Sources
- NASA, 40 Years Ago: Three Months to STS-1, a NASA history post; rewritten in hubnx's own words.
Комментарии

Читать дальше
Ещё на тему «Наука»





