A USGS circular describes a new deposit-size-frequency method for estimating undiscovered uranium endowment, a modification of the standard NURE method, and compares calculations by both methods in its first study area. The circular was written under a September 20, 1984 agreement with the Energy Information Administration (EIA) of the Department of Energy (DOE), and it also sets out a plan to update the national resource base.

Figure 8 of the circular: the conterminous United States, with A-priority (shaded) and B-priority (cross-hatched) 2-degree quadrangles chosen for uranium endowment estimation. Image from the USGS circular.
Why the Survey was back in the business
The 1984 memorandum of understanding between the EIA and the USGS supported the EIA's work under Public Law 97-415 of January 4, 1983, to provide information on the viability of the domestic uranium mining and milling industry. It built on a November 12, 1983 DOE-Interior agreement about data from the National Uranium Resource Evaluation (NURE) Program. It returned to the USGS full responsibility for the geology and resources of uranium, taken from it by the Atomic Energy Act of 1946, so that uranium was treated like other minerals under the USGS Organic Act of 1889. The DOE's program at its Grand Junction office, including NURE, closed in fiscal year 1983, and the data and responsibility passed to the USGS. As of January 1, 1984, the DOE had over 700 individual estimates of potential resources.
Three steps, with the Survey doing the first two
Assessing undiscovered uranium follows three steps:
- Rank an area's geologic favorability, by analogy with settings that hold known deposits: favorable, unfavorable or, if poorly known, uncertain.
- Make a subjective probabilistic estimate of the area's undiscovered endowment, mostly by comparison with known deposits in a "control area". Endowment here means the uranium in recognizable concentrations in rocks averaging at least 0.01 percent uranium oxide.
- Evaluate the economics, which depends on grade cutoff, thickness, depth and mining and milling costs.
The USGS handled the first two; the EIA handled the third.
The old equation and its weak spot
The standard NURE method multiplies five factors: the favorable area (A), the fraction of it underlain by endowment (F), the tons of endowed rock per square mile (T), the average grade (G) and a probability that deposits exist (P). Estimates come from a team of "elicitors" who question the principal scientist and adjust until everyone agrees the result is reasonable. A computer program handles the uncertainty in F, T and G.
F was the trouble. It varies the most, it is the hardest to estimate and was usually the factor adjusted most. It also depends on where the boundary of the favorable area is drawn. The difficulty came from the quality of data, the amount of exploration, how well the deposit type was understood and the size of the area, and in practice geologists mostly judged how many more of the best-known, usually largest, deposits might exist.
The new "deposit-size-frequency" method
The USGS replaced F and T with an explicit count of deposits in each size class, in effect the spatial density of deposits compared with a control area, and replaced P with an optional scaling factor, L. Deposits are real objects with sizes, whereas F is an abstraction, and geologists think about deposits, not fractions. A principal scientist picks one of three options:
- Option A: the favorable area is examined in enough detail to estimate the number and size of deposits directly.
- Option B: it has been examined only cursorily, but enough to estimate deposit densities by reference to a control area.
- Option C: only part of it, a "proto-control area", has been examined in detail, and L expresses how the whole compares with that part. Because L is usually much less than 1.0, option C gives the widest range of results.
An assessment runs through seven steps: judge favorability, choose a control area, develop grade-tonnage data, develop deposit-size-frequency data, choose an option and estimate the factors, calculate the endowment, and put it through expert peer review. Each endowment is also divided among depth ranges down to a maximum of 5,000 ft. The elicitation leaves an audit trail of area, control area, estimates and calculation, and the estimate can be judged by it.
A test in Washington and Idaho
The Survey compared the two methods on the Colville-Okanogan region of Washington and Idaho, where a project chief had nearly completed a study. Its favorable ground is scattered patches of Tertiary granite and the sediments around them. The region contains a few known "young organic-rich" uranium deposits, a class recognized only after 1983 and thought to have high potential for production at comparatively low cost, so no control area existed. The team used the Lake Gillette quadrangle, home of the best-known deposit, Flodelle Creek, as a proto-control area.
| Method | Mean endowment | Range with 9-to-1 odds |
|---|---|---|
| Standard NURE | 8,018 tons | 1,977 to 24,721 tons |
| Deposit-size-frequency | 35,299 tons | 6,738 to 122,320 tons |
The new method gave a larger estimate, 4.4 times the old, and a spread 5.1 times wider. The authors read this as general: the more the inputs are broken down and based on geologic criteria, the larger the expected value and the greater the uncertainty. They concluded the new method uses the scientist's geologic knowledge in a less subjective way and is at least a qualitative improvement.
The plan to update the national base
Private uranium exploration had declined, but the work done had produced new geologic data. The Survey picked four environments for assessment in 1984: young surficial deposits across the conterminous United States, collapse-breccia pipes in the Grand Canyon region of Arizona, Tertiary sedimentary rocks of the Northern Great Plains, and metamorphic rocks of the Piedmont in the eastern United States. For them it selected 64 two-degree quadrangle maps for endowment estimation: 28 "A priority", most likely to add more than 500 tons to the resource base, and 36 "B priority". The schedule was uncertain because of limits on budget and personnel. The Survey also contributes geologic data on uranium and thorium to the biennial international "Red Book" of the OECD's Nuclear Energy Agency and the International Atomic Energy Agency.