A spilled oxidizer cost space shuttle Columbia a month. On September 22, 1981, during fueling of the starboard Forward Reaction Control System, a set of thrusters on the nose, about three gallons of highly toxic and corrosive nitrogen tetroxide spilled onto the orbiter at Launch Pad 39A. NASA's history page describes how that pushed STS-2, Columbia's second flight, from October 9 to November 4, 1981.

Image from NASA's page: Engle, left, and Truly in the Motion Base Simulator at the Johnson Space Center in Houston.
What went wrong
Columbia arrived on Pad 39A on August 31, 1981, and preflight work was going normally. It included a countdown demonstration test, essentially a full dress rehearsal in which Engle and Truly sat in the cockpit as if on launch day, and a practice loading of super-cold liquid hydrogen and liquid oxygen into the external tank. Then the spill happened. The oxidizer seeped between the tiles of the thermal protection system and essentially melted the glue holding them in place, and approximately 370 tiles either fell off or had to be removed so the area could be cleaned of residue.

Image from NASA's page: Columbia on Pad 39A.
The cleanup

Image from NASA's page: the astronauts and the launch director discussing the work on Columbia.
By September 30 engineers had finished cleaning the Forward Reaction Control System module and were replacing tiles at about 30 a day, completing all the missing tiles by mid-October. Fault analysis found deposits of iron nitrate on quick disconnect valves, so workers had to filter the oxidizer before reloading it. As an added precaution, engineers also drained, filtered and reloaded the nearly 15,000 pounds of nitrogen tetroxide in the shuttle's two Orbital Maneuvering System pods to prevent any buildup of iron oxide deposits. That extra work led program managers to move the launch from October 9 to November 4. Engle and Truly used the time to practice mission phases in flight simulators at the Johnson Space Center.

Image from NASA's page: work on the Forward Reaction Control System before refueling.
Meanwhile, STS-3
Work for Columbia's third mission, STS-3, planned for March 1982, was already underway. Its crew, Jack R. Lousma and C. Gordon Fullerton, practiced in the flight simulators at the Johnson Space Center. The STS-3 external tank arrived at the Kennedy Space Center on October 5, 1981, notable for its orange color against the white tanks of STS-1 and STS-2. Managers chose to stop painting the tanks beginning with STS-3, saving about 600 pounds that could go to additional upmass capability. Engineers also prepared the Office of Space Science-1 payload for that flight.

Image from NASA's page: the STS-3 crew in a simulator.

Image from NASA's page: the STS-3 external tank on arrival.

Image from NASA's page: engineers testing the payload for STS-3.
Sources
- NASA, "40 Years Ago: One Month until Space Shuttle Columbia's Return to Space on STS-2" (https://www.nasa.gov/history/40-years-ago-one-month-until-space-shuttle-columbias-return-to-space-on-sts-2/), public domain as a work of the United States government; the page's list of world events in October 1981 is left out; rewritten in hubnx's own words.