Learning Objectives
By the end of this section, you will be able to:
- Write chemical equations and equilibrium expressions representing solubility equilibria
- Carry out equilibrium computations involving solubility, equilibrium expressions, and solute concentrations
The preservation of medical laboratory blood samples, mining of sea water for magnesium, formulation of over-the-counter medicines such as Milk of Magnesia and antacids, and treating the presence of hard water in your home’s water supply are just a few of the many tasks that involve controlling the equilibrium between a slightly soluble ionic solid and an aqueous solution of its ions.
In some cases, we want to prevent
dissolution from occurring. Tooth decay, for example, occurs when the calcium hydroxylapatite, which has the formula Ca5(PO4)3(OH), in our teeth dissolves. The dissolution process is aided when bacteria in our mouths feast on the sugars in our diets to produce lactic acid, which reacts with the hydroxide ions in the calcium hydroxylapatite. Preventing the dissolution prevents the decay. On the other hand, sometimes we want a substance to dissolve. We want the calcium carbonate in a chewable antacid to dissolve because the {\text{CO}}_{3} {}^{\text{2−}} ions produced in this process help soothe an upset stomach.
In this section, we will find out how we can control the dissolution of a slightly soluble ionic solid by the application of Le Châtelier’s principle. We will also learn how to use the equilibrium constant of the reaction to determine the concentration of ions present in a saturated solution.
The Solubility Product
Silver chloride is what’s known as a sparingly soluble ionic solid (Figure 15.2). Recall from the solubility rules in an earlier chapter that halides of Ag+ are not normally soluble. However, when we add an excess of solid AgCl to water, it dissolves to a small extent and produces a mixture consisting of a very dilute solution of Ag+ and Cl– ions in equilibrium with undissolved silver chloride:
\text{AgCl} ( s ) {⇌}_{\text{precipitation}}^{\text{dissolution}} {\text{Ag}}^{\text{+}} ( a q ) + {\text{Cl}}^{\text{−}} ( a q )15.1
This equilibrium, like other equilibria, is dynamic; some of the solid AgCl continues to dissolve, but at the same time, Ag+ and Cl– ions in the solution combine to produce an equal amount of the solid. At equilibrium, the opposing processes have equal rates.

Figure 15.2. Silver chloride is a sparingly soluble ionic solid. When it is added to water, it dissolves slightly and produces a mixture consisting of a very dilute solution of Ag + and Cl – ions in equilibrium with undissolved silver chloride.
The equilibrium constant for the equilibrium between a slightly soluble ionic solid and a solution of its ions is called the solubility product (Ksp) of the solid. Recall from the chapter on solutions and colloids that we use an ion’s concentration as an approximation of its activity in a dilute solution. For silver chloride, at equilibrium:
\text{AgCl} ( s ) ⇌ {\text{Ag}}^{\text{+}} ( a q ) + {\text{Cl}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Ag}}^{\text{+}} ( a q ) ] [ {\text{Cl}}^{\text{−}} ( a q ) ]15.2
Note that the Ksp expression does not contain a term in the denominator for the concentration of the reactant, AgCl. According to the guidelines for deriving mass-action expressions described in an earlier chapter on equilibrium, only gases and solutes are represented. Solids and liquids are assigned concentration values of one and thus do not appear in equilibrium constant expressions; therefore, [AgCl] does not appear in the expression for Ksp.
Some common solubility products are listed in Table 15.1 according to their Ksp values, whereas a more extensive compilation of solubility products appears in Appendix J. Each of these equilibrium constants is much smaller than 1 because the compounds listed are only slightly soluble. A small Ksp represents a system in which the equilibrium lies to the left, so that relatively few hydrated ions would be present in a saturated solution.
| Common Solubility Products by Decreasing Equilibrium Constants | |
|---|---|
| Substance | K sp at 25 °C |
| CuCl | 1.2 × 10 –6 |
| CuBr | 6.27 × 10 –9 |
| AgI | 1.5 × 10 –16 |
| PbS | 7 × 10 –29 |
| Al(OH) 3 | 2 × 10 –32 |
| Fe(OH) 3 | 4 × 10 –38 |
Table 15.1
Example
15.1
Writing Equations and Solubility Products
Write the ionic equation for the dissolution and the solubility product expression for each of the following slightly soluble ionic compounds:
(a) AgI, silver iodide, a solid with antiseptic properties
(b) CaCO3, calcium carbonate, the active ingredient in many over-the-counter chewable antacids
(c) Mg(OH)2, magnesium hydroxide, the active ingredient in Milk of Magnesia
(d) Mg(NH4)PO4, magnesium ammonium phosphate, an essentially insoluble substance used in tests for magnesium
(e) Ca5(PO4)3OH, the mineral apatite, a source of phosphate for fertilizers
(Hint: When determining how to break (d) and (e) up into ions, refer to the list of polyatomic ions in the section on chemical nomenclature.)
Solution
(a) \text{AgI} ( s ) ⇌ {\text{Ag}}^{\text{+}} ( a q ) + {\text{I}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = {[ \text{Ag}}^{\text{+}} ] [ {\text{I}}^{\text{−}} ]
(b) {\text{CaCO}}_{3} ( s ) ⇌ {\text{Ca}}^{\text{2+}} ( a q ) + {\text{CO}}_{3} {}^{\text{2−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Ca}}^{\text{2+}} {] [ \text{CO}}_{3} {}^{\text{2−}} ]
(c) {\text{Mg} ( \text{OH} )}_{2} ( s ) ⇌ {\text{Mg}}^{\text{2+}} ( a q ) + {\text{2OH}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Mg}}^{\text{2+}} ] {[ {\text{OH}}^{\text{−}} ]}^{2}
(d) \text{Mg} ( {\text{NH}}_{\text{4}} ) {\text{PO}}_{\text{4}} ( s ) ⇌ {\text{Mg}}^{\text{2+}} ( a q ) + {\text{NH}}_{4} {}^{\text{+}} ( a q ) + {\text{PO}}_{4} {}^{\text{3−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Mg}}^{\text{2+}} {] [ \text{NH}}_{4} {}^{\text{+}} ] {[ \text{PO}}_{4} {}^{\text{3−}} ]
(e) {\text{Ca}}_{5} ( {\text{PO}}_{4} ) 3 \text{OH} ( s ) ⇌ {\text{5Ca}}^{\text{2+}} ( a q ) + {\text{3PO}}_{4} {}^{\text{3−}} ( a q ) + {\text{OH}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = {{[ \text{Ca}}^{\text{2+}} ]}^{5} [ \text{P} {\text{O}}_{4} {}^{\text{3−}} {]}^{3} [ {\text{OH}}^{\text{−}} ]
Check Your Learning
Write the ionic equation for the dissolution and the solubility product for each of the following slightly soluble compounds:
(a) BaSO4
(b) Ag2SO4
(c) Al(OH)3
(d) Pb(OH)Cl
Answer:
(a) {\text{BaSO}}_{4} ( s ) ⇌ {\text{Ba}}^{\text{2+}} ( a q ) + {\text{SO}}_{4} {}^{\text{2−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Ba}}^{\text{2+}} {] [ \text{SO}}_{4} {{}^{2}}^{\text{−}} ] ; (b) {\text{Ag}}_{2} {\text{SO}}_{4} ( s ) ⇌ {\text{2Ag}}^{\text{+}} ( a q ) + {\text{SO}}_{4} {}^{\text{2−}} ( a q ) \ {K}_{\text{sp}} = {[ {\text{Ag}}^{\text{+}} ]}^{2} [ {\text{SO}}_{4} {}^{\text{2−}} ] ;
(c) {\text{Al} ( \text{OH} )}_{3} ( s ) ⇌ {\text{Al}}^{\text{3+}} ( a q ) + {\text{3OH}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Al}}^{\text{3+}} ] {[ \text{OH}}^{\text{−}} {]}^{\text{3}} ; (d) \text{Pb(OH)Cl(} s ) ⇌ {\text{Pb}}^{\text{2+}} ( a q ) + {\text{OH}}^{\text{−}} ( a q ) + {\text{Cl}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = [ {\text{Pb}}^{\text{2+}} ] {[ \text{OH}}^{\text{−}} ] [ {\text{Cl}}^{\text{−}} ]
Now we will extend the discussion of Ksp and show how the solubility product is determined from the solubility of its ions, as well as how Ksp can be used to determine the molar solubility of a substance.
Ksp and Solubility
The Ksp of a slightly soluble ionic compound may be simply related to its measured solubility provided the dissolution process involves only dissociation and solvation, for example:
{\text{M}}_{p} {\text{X}}_{q} ( s ) ⇌ p {\text{M}}^{\text{m+}} ( a q ) + q {\text{X}}^{\text{n−}} ( a q )15.3
For cases such as these, one may derive Ksp values from provided solubilities, or vice-versa. Calculations of this sort are most conveniently performed using a compound’s molar solubility, measured as moles of dissolved solute per liter of saturated solution.
Example
15.2
Calculation of Ksp from Equilibrium Concentrations
We began the chapter with an informal discussion of how the mineral fluorite (Figure 15.1) is formed. Fluorite, CaF2, is a slightly soluble solid that dissolves according to the equation:
{\text{CaF}}_{2} ( s ) ⇌ {\text{Ca}}^{\text{2+}} ( a q ) + {\text{2F}}^{\text{−}} ( a q )15.4
The concentration of Ca2+ in a saturated solution of CaF2 is 2.15 × 10–4 M; therefore, that of F– is 4.30 × 10–4 M, that is, twice the concentration of Ca2+. What is the solubility product of fluorite?
Solution
First, write out the Ksp expression, then substitute in concentrations and solve for Ksp:
{\text{CaF}}_{2} ( s ) ⇌ {\text{Ca}}^{\text{2+}} ( a q ) + {\text{2F}}^{\text{−}} ( a q )15.5
A saturated solution is a solution at equilibrium with the solid. Thus:
{K}_{\text{sp}} = [ {\text{Ca}}^{\text{2+}} ] {[ {\text{F}}^{\text{−}} ]}^{2} = \text{(2.15} \ × \ {10}^{− 4} ) {( 4.30 \ × \ {10}^{− 4} )}^{2} = \text{3.98} \ × \ {10}^{− 11}15.6
As with other equilibrium constants, we do not include units with Ksp.
Check Your Learning
In a saturated solution that is in contact with solid Mg(OH)2, the concentration of Mg2+ is 1.31 × 10–4 M. What is the solubility product for Mg(OH)2?
{\text{Mg(OH)}}_{2} ( s ) ⇌ {\text{Mg}}^{\text{2+}} ( a q ) + {\text{2OH}}^{\text{−}} ( a q )15.7
Answer:
8.99 × 10–12
Example
15.3
Determination of Molar Solubility from Ksp
The Ksp of copper(I) bromide, CuBr, is 6.3 × 10–9. Calculate the molar solubility of copper bromide.
Solution
The solubility product of copper(I) bromide is 6.3 × 10–9.
The reaction is:
\text{CuBr} ( s ) ⇌ {\text{Cu}}^{\text{+}} ( a q ) + {\text{Br}}^{\text{−}} ( a q )15.8
First, write out the solubility product expression:
{K}_{\text{sp}} = [ {\text{Cu}}^{\text{+}} ] [ {\text{Br}}^{\text{−}} ]15.9
Create an ICE table (as introduced in the chapter on fundamental equilibrium concepts), leaving the CuBr column empty as it is a solid and does not contribute to the Ksp:

At equilibrium:
{K}_{\text{sp}} = {[ \text{Cu}}^{\text{+}} ] [ {\text{Br}}^{\text{−}} ]15.10
6.3 \ × \ {10}^{− 9} = ( x ) ( x ) = {x}^{2}15.11
x = \sqrt{( 6.3 \ × \ {10}^{− 9} )} = \text{7.9} \ × \ {10}^{− 5}15.12
Therefore, the molar solubility of CuBr is 7.9 × 10–5 M.
Check Your Learning
The Ksp of AgI is 1.5 × 10–16. Calculate the molar solubility of silver iodide.
Answer:
1.2 × 10–8 M
Example
15.4
Determination of Molar Solubility from Ksp, Part II
The Ksp of calcium hydroxide, Ca(OH)2, is 1.3 × 10–6. Calculate the molar solubility of calcium hydroxide.
Solution
The solubility product of calcium hydroxide is 1.3 × 10–6.The reaction is:
{\text{Ca(OH)}}_{2} ( s ) ⇌ {\text{Ca}}^{\text{2+}} ( a q ) + {\text{2OH}}^{\text{−}} ( a q )15.13
First, write out the solubility product expression:
{K}_{\text{sp}} = [ {\text{Ca}}^{\text{2+}} ] {[ {\text{OH}}^{\text{−}} ]}^{2}15.14
Create an ICE table, leaving the Ca(OH)2 column empty as it is a solid and does not contribute to the Ksp:

At equilibrium:
{K}_{\text{sp}} = [ {\text{Ca}}^{\text{2+}} ] {[ {\text{OH}}^{\text{−}} ]}^{2}15.15
1.3 \ × \ {10}^{− 6 \text{}} = ( x ) ( 2 x {)}^{2} = ( x ) ( 4 {x}^{2} ) = 4 {x}^{3}15.16
x = \sqrt[3]{\ \frac{1.3 \ × \ {10}^{− 6}}{4} \ } = \text{6.9} \ × \ {10}^{− 3}15.17
Therefore, the molar solubility of Ca(OH)2 is 6.9 × 10–3 M.
Check Your Learning
The Ksp of PbI2 is 1.4 × 10–8. Calculate the molar solubility of lead(II) iodide.
Answer:
1.5 × 10–3 M
Note that solubility is not always given as a molar value. When the solubility of a compound is given in some unit other than moles per liter, we must convert the solubility into moles per liter (i.e., molarity) in order to use it in the solubility product expression. Example 15.5 shows how to perform those unit conversions before determining the solubility product equilibrium.
Example
15.5
Determination of Ksp from Gram Solubility
Many of the pigments used by artists in oil-based paints (Figure 15.3) are sparingly soluble in water. For example, the solubility of the artist’s pigment chrome yellow, PbCrO4, is 4.6 × 10–6 g/L. Determine the solubility product for PbCrO4.

Figure 15.3. Oil paints contain pigments that are very slightly soluble in water. In addition to chrome yellow (PbCrO 4 ), examples include Prussian blue (Fe 7 (CN) 18 ), the reddish-orange color vermilion (HgS), and green color veridian (Cr 2 O 3 ). (credit: Sonny Abesamis)
Solution
We are given the solubility of PbCrO4 in grams per liter. If we convert this solubility into moles per liter, we can find the equilibrium concentrations of Pb2+ and {\text{CrO}}_{4} {}^{\text{2−}} , then Ksp:

- Step 1.
Use the molar mass of PbCrO4( \frac{323.2 \ \text{g}}{1 \ \text{mol}} )to convert the solubility of PbCrO4 in grams per liter into moles per liter:
\begin{matrix} \\ \\ [ {\text{PbCrO}}_{4} ] = \frac{4.6 \ × \ {10}^{− 6} {\text{g PbCrO}}_{4}}{1 \ \text{L}} \ \ × \ \ \frac{1 {\ \text{mol PbCrO}}_{4}}{323.2 {\ \text{g PbCrO}}_{4}} \ \\ = \ \frac{1.4 \ × \ {10}^{− 8} {\ \text{mol PbCrO}}_{4}}{1 \ \text{L}} \ \\ = \ 1.4 \ × \ {10}^{− 8} M\end{matrix}15.18
- Step 2.
The chemical equation for the dissolution indicates that 1 mol of PbCrO4 gives 1 mol of Pb2+(aq) and 1 mol of{\text{CrO}}_{4} {}^{\text{2−}} ( a q ) \text{:}
{\text{PbCrO}}_{4} ( s ) ⇌ {\text{Pb}}^{\text{2+}} ( a q ) + {\text{CrO}}_{4} {}^{\text{2−}} ( a q )15.19
Thus, both [Pb2+] and [ {\text{CrO}}_{4} {}^{\text{2−}} ] are equal to the molar solubility of PbCrO4:
[ {\text{Pb}}^{\text{2+}} ] = [ {\text{CrO}}_{4} {}^{\text{2−}} ] = \text{1.4} \ × \ {10}^{− 8} M15.20
- Step 3.
Solve. Ksp = [Pb2+][ {\text{CrO}}_{4} {}^{\text{2−}} ]= (1.4×10–8)(1.4×10–8) = 2.0×10–16
Check Your Learning
The solubility of TlCl [thallium(I) chloride], an intermediate formed when thallium is being isolated from ores, is 3.46 grams per liter at 20 °C. What is its solubility product?
Answer:
2.08 × 10–4
Example
15.6
Calculating the Solubility of Hg2Cl2
Calomel, Hg2Cl2, is a compound composed of the diatomic ion of mercury(I), {\text{Hg}}_{2} {}^{\text{2+}} , and chloride ions, Cl–. Although most mercury compounds are now known to be poisonous, eighteenth-century physicians used calomel as a medication. Their patients rarely suffered any mercury poisoning from the treatments because calomel is quite insoluble:
{\text{Hg}}_{2} {\text{Cl}}_{2} ( s ) ⇌ {\text{Hg}}_{2} {}^{\text{2+}} ( a q ) + {\text{2Cl}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = \text{1.1} \ × \ {10}^{− 18}15.21
Calculate the molar solubility of Hg2Cl2.
Solution
The molar solubility of Hg2Cl2 is equal to the concentration of {\text{Hg}}_{2} {}^{\text{2+}} ions because for each 1 mol of Hg2Cl2 that dissolves, 1 mol of {\text{Hg}}_{2} {}^{\text{2+}} forms:

- Step 1.
Determine the direction of change. Before any Hg2Cl2 dissolves, Q is zero, and the reaction will shift to the right to reach equilibrium. - Step 2.
Determine x and equilibrium concentrations. Concentrations and changes are given in the following ICE table:

Note that the change in the concentration of Cl– (2x) is twice as large as the change in the concentration of {\text{Hg}}_{2} {}^{\text{2+}} (x) because 2 mol of Cl– forms for each 1 mol of {\text{Hg}}_{2} {}^{\text{2+}} that forms. Hg2Cl2 is a pure solid, so it does not appear in the calculation.
- Step 3.
Solve for x and the equilibrium concentrations. We substitute the equilibrium concentrations into the expression for Ksp and calculate the value of x:
{K}_{\text{sp}} = [ {\text{Hg}}_{\text{2}} {}^{\text{2+}} ] {[ {\text{Cl}}^{\text{−}} ]}^{2}15.22
1.1 \ × \ {10}^{− 18} = ( x ) ( 2 x {)}^{2}15.23
4 {x}^{3} = \text{1.1} \ × \ {10}^{− 18}15.24
x = \sqrt[3]{( \frac{1.1 \ × \ {10}^{− 18}}{4} )} = \text{6.5} \ × \ {10}^{− 7} \ M15.25
[ {\text{Hg}}_{2} {}^{\text{2+}} ] = \text{6.5} \ × \ {10}^{− 7} \ M = \text{6.5} \ × \ {10}^{− 7} \ M15.26
[ {\text{Cl}}^{\text{−}} ] = 2 x = \text{2(6.5} \ × \ {10}^{− 7} ) = 1.3 \ × \ {10}^{− 6} \ M15.27
The molar solubility of Hg2Cl2 is equal to [ {\text{Hg}}_{\text{2}} {}^{\text{2+}} ] , or 6.5 × 10–7 M.
- Step 4.
Check the work. At equilibrium, Q = Ksp:
Q = [ {\text{Hg}}_{\text{2}} {}^{\text{2+}} ] {[ {\text{Cl}}^{\text{−}} ]}^{2} = \text{(6.5} \ × \ {10}^{− 7} ) {( 1.3 \ × \ {10}^{− 6} )}^{2} = 1.1 \ × \ {10}^{− 18}15.28
The calculations check.
Check Your Learning
Determine the molar solubility of MgF2 from its solubility product: Ksp = 6.4 × 10–9.
Answer:
1.2 × 10–3 M
Tabulated Ksp values can also be compared to reaction quotients calculated from experimental data to tell whether a solid will precipitate in a reaction under specific conditions: Q equals Ksp at equilibrium; if Q is less than Ksp, the solid will dissolve until Q equals Ksp; if Q is greater than Ksp, precipitation will occur at a given temperature until Q equals Ksp.
How Sciences Interconnect
Using Barium Sulfate for Medical Imaging
Various types of medical imaging techniques are used to aid diagnoses of illnesses in a noninvasive manner. One such technique utilizes the ingestion of a barium compound before taking an X-ray image. A suspension of barium sulfate, a chalky powder, is ingested by the patient. Since the Ksp of barium sulfate is 1.1 × 10–10, very little of it dissolves as it coats the lining of the patient’s intestinal tract. Barium-coated areas of the digestive tract then appear on an X-ray as white, allowing for greater visual detail than a traditional X-ray (Figure 15.4).

Figure 15.4. The suspension of barium sulfate coats the intestinal tract, which allows for greater visual detail than a traditional X-ray. (credit modification of work by “glitzy queen00”/Wikimedia Commons)
Further diagnostic testing can be done using barium sulfate and fluoroscopy. In fluoroscopy, a continuous X-ray is passed through the body so the doctor can monitor, on a TV or computer screen, the barium sulfate’s movement as it passes through the digestive tract. Medical imaging using barium sulfate can be used to diagnose acid reflux disease, Crohn’s disease, and ulcers in addition to other conditions.
Visit this website for more information on how barium is used in medical diagnoses and which conditions it is used to diagnose.
Predicting Precipitation
The equation that describes the equilibrium between solid calcium carbonate and its solvated ions is:
{\text{CaCO}}_{3} ( s ) ⇌ {\text{Ca}}^{\text{2+}} ( a q ) + {\text{CO}}_{3} {}^{\text{2−}} ( a q )15.29
We can establish this equilibrium either by adding solid calcium carbonate to water or by mixing a solution that contains calcium ions with a solution that contains carbonate ions. If we add calcium carbonate to water, the solid will dissolve until the concentrations are such that the value of the reaction quotient ( \text{Q} = [ {\text{Ca}}^{2 +} ] [ {\text{CO}}_{3} {}^{\text{2−}} ] ) is equal to the solubility product (Ksp = 8.7 × 10–9). If we mix a solution of calcium nitrate, which contains Ca2+ ions, with a solution of sodium carbonate, which contains {\text{CO}}_{3} {}^{\text{2−}} ions, the slightly soluble ionic solid CaCO3 will precipitate, provided that the concentrations of Ca2+ and {\text{CO}}_{3} {}^{\text{2−}} ions are such that Q is greater than Ksp for the mixture. The reaction shifts to the left and the concentrations of the ions are reduced by formation of the solid until the value of Q equals Ksp. A saturated solution in equilibrium with the undissolved solid will result. If the concentrations are such that Q is less than Ksp, then the solution is not saturated and no precipitate will form.
We can compare numerical values of Q with Ksp to predict whether precipitation will occur, as Example 15.7 shows. (Note: Since all forms of equilibrium constants are temperature dependent, we will assume a room temperature environment going forward in this chapter unless a different temperature value is explicitly specified.)
Example
15.7
Precipitation of Mg(OH)2
The first step in the preparation of magnesium metal is the precipitation of Mg(OH)2 from sea water by the addition of lime, Ca(OH)2, a readily available inexpensive source of OH– ion:
{\text{Mg(OH)}}_{2} ( s ) ⇌ {\text{Mg}}^{\text{2+}} ( a q ) + {\text{2OH}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = \text{8.9} \ × \ {10}^{− 12}15.30
The concentration of Mg2+(aq) in sea water is 0.0537 M. Will Mg(OH)2 precipitate when enough Ca(OH)2 is added to give a [OH–] of 0.0010 M?
Solution
This problem asks whether the reaction:
{\text{Mg(OH)}}_{2} ( s ) ⇌ {\text{Mg}}^{\text{2+}} ( a q ) + {\text{2OH}}^{\text{−}} ( a q )15.31
shifts to the left and forms solid Mg(OH)2 when [Mg2+] = 0.0537 M and [OH–] = 0.0010 M. The reaction shifts to the left if Q is greater than Ksp. Calculation of the reaction quotient under these conditions is shown here:
Q = [ {\text{Mg}}^{\text{2+}} ] {[ {\text{OH}}^{\text{−}} ]}^{2} = \text{(0.0537)(} {\text{0.0010)}}^{2} = \text{5.4} \ × \ {10}^{− 8}15.32
Because Q is greater than Ksp (Q = 5.4 × 10–8 is larger than Ksp = 8.9 × 10–12), we can expect the reaction to shift to the left and form solid magnesium hydroxide. Mg(OH)2(s) forms until the concentrations of magnesium ion and hydroxide ion are reduced sufficiently so that the value of Q is equal to Ksp.
Check Your Learning
Use the solubility product in Appendix J to determine whether CaHPO4 will precipitate from a solution with [Ca2+] = 0.0001 M and [ {\text{HPO}}_{4} {}^{\text{2−}} ] = 0.001 M.
Answer:
No precipitation of CaHPO4; Q = 1 × 10–7, which is less than Ksp
Example
15.8
Precipitation of AgCl upon Mixing Solutions
Does silver chloride precipitate when equal volumes of a 2.0 × 10–4-M solution of AgNO3 and a 2.0 × 10–4-M solution of NaCl are mixed?
(Note: The solution also contains Na+ and {\text{NO}}_{3} {}^{\text{−}} ions, but when referring to solubility rules, one can see that sodium nitrate is very soluble and cannot form a precipitate.)
Solution
The equation for the equilibrium between solid silver chloride, silver ion, and chloride ion is:
\text{AgCl} ( s ) ⇌ {\text{Ag}}^{\text{+}} ( a q ) + {\text{Cl}}^{\text{−}} ( a q )15.33
The solubility product is 1.6 × 10–10 (see Appendix J).
AgCl will precipitate if the reaction quotient calculated from the concentrations in the mixture of AgNO3 and NaCl is greater than Ksp. The volume doubles when we mix equal volumes of AgNO3 and NaCl solutions, so each concentration is reduced to half its initial value. Consequently, immediately upon mixing, [Ag+] and [Cl–] are both equal to:
\frac{1}{2} ( 2.0 \ × \ {10}^{− 4} ) \ M = \text{1.0} \ × \ {10}^{− 4} \ M15.34
The reaction quotient, Q, is momentarily greater than Ksp for AgCl, so a supersaturated solution is formed:
Q = [ {\text{Ag}}^{\text{+}} ] {[ \text{Cl}}^{\text{−}} ] = \text{(1.0} \ × \ {10}^{− 4} ) ( 1.0 \ × \ {10}^{− 4} ) = \text{1.0} \ × \ {10}^{− 8} > {K}_{\text{sp}}15.35
Since supersaturated solutions are unstable, AgCl will precipitate from the mixture until the solution returns to equilibrium, with Q equal to Ksp.
Check Your Learning
Will KClO4 precipitate when 20 mL of a 0.050-M solution of K+ is added to 80 mL of a 0.50-M solution of {\text{ClO}}_{4} {}^{\text{−}} ? (Remember to calculate the new concentration of each ion after mixing the solutions before plugging into the reaction quotient expression.)
Answer:
No, Q = 4.0 × 10–3, which is less than Ksp = 1.05 × 10–2
In the previous two examples, we have seen that Mg(OH)2 or AgCl precipitate when Q is greater than Ksp. In general, when a solution of a soluble salt of the Mm+ ion is mixed with a solution of a soluble salt of the Xn– ion, the solid, MpXq precipitates if the value of Q for the mixture of Mm+ and Xn– is greater than Ksp for MpXq. Thus, if we know the concentration of one of the ions of a slightly soluble ionic solid and the value for the solubility product of the solid, then we can calculate the concentration that the other ion must exceed for precipitation to begin. To simplify the calculation, we will assume that precipitation begins when the reaction quotient becomes equal to the solubility product.
Example
15.9
Precipitation of Calcium Oxalate
Blood will not clot if calcium ions are removed from its plasma. Some blood collection tubes contain salts of the oxalate ion, {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} , for this purpose (Figure 15.5). At sufficiently high concentrations, the calcium and oxalate ions form solid, CaC2O4·H2O (which also contains water bound in the solid). The concentration of Ca2+ in a sample of blood serum is 2.2 × 10–3 M. What concentration of {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} ion must be established before CaC2O4·H2O begins to precipitate?

Figure 15.5. Anticoagulants can be added to blood that will combine with the Ca 2+ ions in blood serum and prevent the blood from clotting. (credit: modification of work by Neeta Lind)
Solution
The equilibrium expression is:
{\text{CaC}}_{2} {\text{O}}_{4} ( s ) ⇌ {\text{Ca}}^{\text{2+}} ( a q ) + {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} ( a q )15.36
For this reaction:
{K}_{\text{sp}} = [ {\text{Ca}}^{\text{2+}} ] [ {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} ] = 1.96 \ × \ {10}^{− 8}15.37
(see Appendix J)
CaC2O4 does not appear in this expression because it is a solid. Water does not appear because it is the solvent.
Solid CaC2O4 does not begin to form until Q equals Ksp. Because we know Ksp and [Ca2+], we can solve for the concentration of {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} that is necessary to produce the first trace of solid:
Q = {K}_{\text{sp}} = [ {\text{Ca}}^{\text{2+}} ] {[ \text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} ] \ = \text{1.96} \ × \ {10}^{− 8}15.38
( 2.2 \ × \ {10}^{− 3} ) [ {\text{C}}_{\text{2}} {\text{O}}_{4} {}^{\text{2−}} ] = \text{1.96} \ × \ {10}^{− 8}15.39
[ {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} ] = \ \frac{1.96 \ × \ {10}^{− 8}}{2.2 \ × \ {10}^{− 3}} \ = \ \text{8.9} \ × \ {10}^{− 6}15.40
A concentration of [ {\text{C}}_{2} {\text{O}}_{4} {}^{\text{2−}} ] = 8.9 × 10–6 M is necessary to initiate the precipitation of CaC2O4 under these conditions.
Check Your Learning
If a solution contains 0.0020 mol of {\text{CrO}}_{4} {}^{\text{2−}} per liter, what concentration of Ag+ ion must be reached by adding solid AgNO3 before Ag2CrO4 begins to precipitate? Neglect any increase in volume upon adding the solid silver nitrate.
Answer:
4.5 × 10–9 M
It is sometimes useful to know the concentration of an ion that remains in solution after precipitation. We can use the solubility product for this calculation too: If we know the value of Ksp and the concentration of one ion in solution, we can calculate the concentration of the second ion remaining in solution. The calculation is of the same type as that in Example 15.9—calculation of the concentration of a species in an equilibrium mixture from the concentrations of the other species and the equilibrium constant. However, the concentrations are different; we are calculating concentrations after precipitation is complete, rather than at the start of precipitation.
Example
15.10
Concentrations Following Precipitation
Clothing washed in water that has a manganese [Mn2+(aq)] concentration exceeding 0.1 mg/L (1.8 × 10–6 M) may be stained by the manganese upon oxidation, but the amount of Mn2+ in the water can be reduced by adding a base. If a person doing laundry wishes to add a buffer to keep the pH high enough to precipitate the manganese as the hydroxide, Mn(OH)2, what pH is required to keep [Mn2+] equal to 1.8 × 10–6 M?
Solution
The dissolution of Mn(OH)2 is described by the equation:
{\text{Mn(OH)}}_{2} ( s ) ⇌ {\text{Mn}}^{\text{2+}} ( a q ) + {\text{2OH}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = \text{2} \ × \ {10}^{− 13}15.41
We need to calculate the concentration of OH– when the concentration of Mn2+ is 1.8 × 10–6 M. From that, we calculate the pH. At equilibrium:
{K}_{\text{sp}} = [ {\text{Mn}}^{\text{2+}} ] {[ {\text{OH}}^{\text{−}} ]}^{2}15.42
or
( 1.8 \ × \ {10}^{− 6} ) {[ {\text{OH}}^{\text{−}} ]}^{2} = \text{2} \ × \ {10}^{− 13}15.43
so
[ {\text{OH}}^{\text{−}} ] = \text{3.3} \ × \ {10}^{− 4} \ M15.44
Now we calculate the pH from the pOH:
\begin{matrix}\text{pOH} = \text{−log} [ {\text{OH}}^{\text{−}} ] = \text{−log} ( 3.3 \ × \ 10 − 4 ) = \text{3.48} \\ \text{pH} = \text{14.00} − \text{pOH} = \text{14.00} − \text{3.80} = \text{10.52}\end{matrix}15.45
If the person doing laundry adds a base, such as the sodium silicate (Na4SiO4) in some detergents, to the wash water until the pH is raised to 10.52, the manganese ion will be reduced to a concentration of 1.8 × 10–6 M; at that concentration or less, the ion will not stain clothing.
Check Your Learning
The first step in the preparation of magnesium metal is the precipitation of Mg(OH)2 from sea water by the addition of Ca(OH)2. The concentration of Mg2+(aq) in sea water is 5.37 × 10–2 M. Calculate the pH at which [Mg2+] is diminished to 1.0 × 10–5 M by the addition of Ca(OH)2.
Answer:
10.97
Due to their light sensitivity, mixtures of silver halides are used in fiber optics for medical lasers, in photochromic eyeglass lenses (glass lenses that automatically darken when exposed to sunlight), and—before the advent of digital photography—in photographic film. Even though AgCl (Ksp = 1.6 × 10–10), AgBr (Ksp = 5.0 × 10–13), and AgI (Ksp = 1.5 × 10–16) are each quite insoluble, we cannot prepare a homogeneous solid mixture of them by adding Ag+ to a solution of Cl–, Br–, and I–; essentially all of the AgI will precipitate before any of the other solid halides form because of its smaller value for Ksp. However, we can prepare a homogeneous mixture of the solids by slowly adding a solution of Cl–, Br–, and I– to a solution of Ag+.
When two anions form slightly soluble compounds with the same cation, or when two cations form slightly soluble compounds with the same anion, the less soluble compound (usually, the compound with the smaller Ksp) generally precipitates first when we add a precipitating agent to a solution containing both anions (or both cations). When the Ksp values of the two compounds differ by two orders of magnitude or more (e.g., 10–2 vs. 10–4), almost all of the less soluble compound precipitates before any of the more soluble one does. This is an example of selective precipitation, where a reagent is added to a solution of dissolved ions causing one of the ions to precipitate out before the rest.
Chemistry in Everyday Life
The Role of Precipitation in Wastewater Treatment
Solubility equilibria are useful tools in the treatment of wastewater carried out in facilities that may treat the municipal water in your city or town (Figure 15.6). Specifically, selective precipitation is used to remove contaminants from wastewater before it is released back into natural bodies of water. For example, phosphate ions {\text{(PO}}_{4} {}^{\text{3−}} ) are often present in the water discharged from manufacturing facilities. An abundance of phosphate causes excess algae to grow, which impacts the amount of oxygen available for marine life as well as making water unsuitable for human consumption.

Figure 15.6. Wastewater treatment facilities, such as this one, remove contaminants from wastewater before the water is released back into the natural environment. (credit: “eutrophication&hypoxia”/Wikimedia Commons)
One common way to remove phosphates from water is by the addition of calcium hydroxide, known as lime, Ca(OH)2. As the water is made more basic, the calcium ions react with phosphate ions to produce hydroxylapatite, Ca5(PO4)3OH, which then precipitates out of the solution:
5 {\text{Ca}}^{\text{2+}} + {\text{3PO}}_{4} {}^{\text{3−}} + {\text{OH}}^{\text{−}} ⇌ {\text{Ca}}_{5} {{\text{(PO}}_{4} )}_{\text{3}} \text{·} \text{OH} ( s )15.46
The precipitate is then removed by filtration and the water is brought back to a neutral pH by the addition of CO2 in a recarbonation process. Other chemicals can also be used for the removal of phosphates by precipitation, including iron(III) chloride and aluminum sulfate.
View this site for more information on how phosphorus is removed from wastewater.
Selective precipitation can also be used in qualitative analysis. In this method, reagents are added to an unknown chemical mixture in order to induce precipitation. Certain reagents cause specific ions to precipitate out; therefore, the addition of the reagent can be used to determine whether the ion is present in the solution.
Link to Learning
View this simulation to study the process of salts dissolving and forming saturated solutions and precipitates for specific compounds, or compounds for which you select the charges on the ions and the Ksp
Example
15.11
Precipitation of Silver Halides
A solution contains 0.0010 mol of KI and 0.10 mol of KCl per liter. AgNO3 is gradually added to this solution. Which forms first, solid AgI or solid AgCl?
Solution
The two equilibria involved are:
\text{AgCl} ( s ) ⇌ {\text{Ag}}^{\text{+}} ( a q ) + {\text{Cl}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = \text{1.6} \ × \ {10}^{− 10}15.47
\text{AgI} ( s ) ⇌ {\text{Ag}}^{\text{+}} ( a q ) + {\text{I}}^{\text{−}} ( a q ) \ {K}_{\text{sp}} = \text{1.5} \ × \ {10}^{− 16}15.48
If the solution contained about equal concentrations of Cl– and I–, then the silver salt with the smallest Ksp (AgI) would precipitate first. The concentrations are not equal, however, so we should find the [Ag+] at which AgCl begins to precipitate and the [Ag+] at which AgI begins to precipitate. The salt that forms at the lower [Ag+] precipitates first.
For AgI: AgI precipitates when Q equals Ksp for AgI (1.5 × 10–16). When [I–] = 0.0010 M:
Q = [ {\text{Ag}}^{\text{+}} ] {[ \text{I}}^{\text{−}} ] = [ {\text{Ag}}^{+} ] \text{(0.0010)} = \text{1.5} \ × \ {10}^{− 16}15.49
[ {\text{Ag}}^{\text{+}} ] = \ \frac{\text{1.5} \ × \ {10}^{− 16}}{0.10} \ = \text{1.6} \ × \ {10}^{− 9}15.50
AgI begins to precipitate when [Ag+] is 1.6 × 10–9 M.
For AgCl: AgCl precipitates when Q equals Ksp for AgCl (1.6 × 10–10). When [Cl–] = 0.10 M:
{Q}_{\text{sp}} = [ {\text{Ag}}^{\text{+}} ] {[ \text{Cl}}^{\text{−}} ] = [ {\text{Ag}}^{\text{+}} ] \text{(0.10)} = \text{1.6} \ × \ {10}^{− 10}15.51
[ {\text{Ag}}^{\text{+}} ] = \ \frac{1.6 \ × \ {10}^{− 10}}{0.10} = \text{1.6} \ × \ {10}^{− 9} \ M15.52
AgCl begins to precipitate when [Ag+] is 1.6 × 10–9 M.
AgI begins to precipitate at a lower [Ag+] than AgCl, so AgI begins to precipitate first.
Check Your Learning
If silver nitrate solution is added to a solution which is 0.050 M in both Cl– and Br– ions, at what [Ag+] would precipitation begin, and what would be the formula of the precipitate?
Answer:
[Ag+] = 1.0 × 10–11 M; AgBr precipitates first
Common Ion Effect
As we saw when we discussed buffer solutions, the hydronium ion concentration of an aqueous solution of acetic acid decreases when the strong electrolyte sodium acetate, NaCH3CO2, is added. We can explain this effect using Le Châtelier’s principle. The addition of acetate ions causes the equilibrium to shift to the left, decreasing the concentration of {\text{H}}_{3} {\text{O}}^{\text{+}} to compensate for the increased acetate ion concentration. This increases the concentration of CH3CO2H:
{\text{CH}}_{3} {\text{CO}}_{2} \text{H} + {\text{H}}_{2} \text{O} ⇌ {\text{H}}_{3} {\text{O}}^{\text{+}} + {\text{CH}}_{3} {\text{CO}}_{2} {}^{\text{−}}15.53
Because sodium acetate and acetic acid have the acetate ion in common, the influence on the equilibrium is called the common ion effect.
The common ion effect can also have a direct effect on solubility equilibria. Suppose we are looking at the reaction where silver iodide is dissolved:
\text{AgI} ( s ) ⇌ {\text{Ag}}^{\text{+}} ( a q ) + {\text{I}}^{\text{−}} ( a q )15.54
If we were to add potassium iodide (KI) to this solution, we would be adding a substance that shares a common ion with silver iodide. Le Châtelier’s principle tells us that when a change is made to a system at equilibrium, the reaction will shift to counteract that change. In this example, there would be an excess of iodide ions, so the reaction would shift toward the left, causing more silver iodide to precipitate out of solution.
Link to Learning
View this simulation to see how the common ion effect works with different concentrations of salts.
Example
15.12
Common Ion Effect
Calculate the molar solubility of cadmium sulfide (CdS) in a 0.010-M solution of cadmium bromide (CdBr2). The Ksp of CdS is 1.0 × 10–28.
Solution
The first thing you should notice is that the cadmium sulfide is dissolved in a solution that contains cadmium ions. We need to use an ICE table to set up this problem and include the CdBr2 concentration as a contributor of cadmium ions:
\text{CdS} ( s ) ⇌ {\text{Cd}}^{\text{2+}} ( a q ) + {\text{S}}^{\text{2−}} ( a q )15.55

{K}_{\text{sp}} = [ {\text{Cd}}^{\text{2+}} ] [ {\text{S}}^{\text{2−}} ] = 1.0 \ × \ {10}^{− 28}15.56
( 0.010 + x ) ( x ) = \text{1.0} \ × \ {10}^{− 28}15.57
{x}^{2} + \text{0.010} x − \text{1.0} \ × \ {10}^{− 28} = 015.58
We can solve this equation using the quadratic formula, but we can also make an assumption to make this calculation much simpler. Since the Ksp value is so small compared with the cadmium concentration, we can assume that the change between the initial concentration and the equilibrium concentration is negligible, so that 0.010 + x ~ 0.010. Going back to our Ksp expression, we would now get:
{K}_{\text{sp}} = [ {\text{Cd}}^{\text{2+}} ] {[ \text{S}}^{\text{2−}} ] = \text{1.0} \ × \ {10}^{− 28}15.59
( 0.010 ) ( x ) = \text{1.0} \ × \ {10}^{− 28}15.60
x = \text{1.0} \ × \ {10}^{− 26}15.61
Therefore, the molar solubility of CdS in this solution is 1.0 × 10–26 M.
Check Your Learning
Calculate the molar solubility of aluminum hydroxide, Al(OH)3, in a 0.015-M solution of aluminum nitrate, Al(NO3)3. The Ksp of Al(OH)3 is 2 × 10–32.
Answer:
4 × 10–11 M
Where this page came from
This page was imported from OpenStax, Chemistry. Section 15.1 of Chemistry by Paul Flowers, William R. Robinson, PhD, Richard Langley, Klaus Theopold, published by OpenStax (Rice University) under CC BY 4.0; the book is free at openstax.org. Changed here: set as a page on its own.
Nobody has written it yet — it is the source material at a new address, which is why search engines are asked to skip it and why no one earns from it. It is up for grabs: take it on, and it is yours to rewrite and to earn from.
I disse publikationerChemistry (OpenStax)
Licens: CC BY 4.0 · Bearbejdet efter openstax.org
Kommentarer