Space Shuttle Columbia reached the Kennedy Space Center (KSC) from its North American Rockwell manufacturing facility in Palmdale, California, on March 24, 1979, and then spent 19 months being readied for its first flight, STS-1. NASA's history page describes the main jobs: tiles, the external tank, the boosters, the engines, and a string of tests and simulations.
Arrival
Columbia came bolted atop a Boeing 747 Shuttle Carrier Aircraft (SCA) on a four-day transcontinental ferry flight with three overnight stops in Texas and Florida. The next day workers removed it from the SCA and towed it into the Orbiter Processing Facility (OPF). In February 1980 mission managers planned a launch for November of that year but expected it might slip into early 1981.


Left: Columbia atop the SCA touching down at KSC. Right: Columbia in the OPF.
Tiles and the tank
Columbia arrived with many Thermal Protection System tiles missing, and the temporary tiles used for the ferry flight had to be swapped for permanent ones. The tiles were one of the most complex new technologies in the shuttle and stayed the leading challenge in preparing for the flight. Roughly 30,000 tiles, each sized for its own spot, had to be installed and tested for strength and bonding.
The external tank (ET) for STS-1 arrived at KSC in July 1979 by barge from the Michoud assembly plant outside New Orleans and went into a test stand in the Vehicle Assembly Building (VAB) to await stacking.


Left: Engineer applying a tile to Columbia's left wing. Right: The ET for STS-1 arrives at KSC.
Boosters and engines
All the components of the two Solid Rocket Boosters (SRBs) were in the VAB by September 1979, and stacking began. By early January 1980 both were stacked on the Mobile Launch Platform. To qualify the boosters, workers fired the motor four times for demonstration and three times for qualification at Thiokol's Wasatch Facility near Brigham City, Utah. After the final test on Feb. 13, 1980, managers qualified the booster for flight.



All three Space Shuttle Main Engines passed flight qualification and were installed in August 1979. At the National Space Transportation Laboratory in Bay St. Louis, Mississippi, workers ran 3-engine tests with non-flight-qualified engines:
| Date | Result |
|---|---|
| Dec. 17, 1979 | First full-duration test, 554 seconds |
| Feb. 1, 1980 | Ended after 4.6 seconds because one engine started late |
| Feb. 28, 1980 | Repeat, the second of a planned series of seven, ended successfully after 560 seconds |


Tests and simulations
Several hundred NASA and contractor engineers at KSC, Johnson Space Center (JSC) and Rockwell's Downey, California, facility ran Orbiter Integrated Tests (OIT) to exercise orbiter hardware and software through a mission timeline. The first, from Dec. 16 to 20, 1979, included Columbia's first simulated launch and flight into orbit. Prime crew John W. Young and Robert L. Crippen and backups Joe H. Engle and Richard F. Truly took part from inside Columbia, powered up in the OPF. A second, 11-day OIT with five simulated launches and a full 54-hour simulated flight finished successfully on Jan. 18, 1980. Crippen called the shuttle "a really spectacular machine," and Young said Columbia performed "like a champ."

Starting Jan. 24, flight controllers and astronauts also ran a 30-hour simulation from Mission Control at JSC, from a simulated launch and orbital insertion to a simulated landing the next day. About 500 NASA and contractor personnel took part, and the aim was to test operations and procedures over an extended period. More simulations followed at regular intervals.