Space Shuttle Columbia reached the Kennedy Space Center (KSC) from its North American Rockwell manufacturing facility in Palmdale, California, on March 24, 1979, and then spent 19 months being readied for its first flight, STS-1. NASA's history page describes the main jobs: tiles, the external tank, the boosters, the engines, and a string of tests and simulations.

Arrival

Columbia came bolted atop a Boeing 747 Shuttle Carrier Aircraft (SCA) on a four-day transcontinental ferry flight with three overnight stops in Texas and Florida. The next day workers removed it from the SCA and towed it into the Orbiter Processing Facility (OPF). In February 1980 mission managers planned a launch for November of that year but expected it might slip into early 1981.

Columbia atop the Shuttle Carrier Aircraft touching down at the Kennedy Space Center, March 24, 1979.

Columbia in the Orbiter Processing Facility, March 1979.

Left: Columbia atop the SCA touching down at KSC. Right: Columbia in the OPF.

Tiles and the tank

Columbia arrived with many Thermal Protection System tiles missing, and the temporary tiles used for the ferry flight had to be swapped for permanent ones. The tiles were one of the most complex new technologies in the shuttle and stayed the leading challenge in preparing for the flight. Roughly 30,000 tiles, each sized for its own spot, had to be installed and tested for strength and bonding.

The external tank (ET) for STS-1 arrived at KSC in July 1979 by barge from the Michoud assembly plant outside New Orleans and went into a test stand in the Vehicle Assembly Building (VAB) to await stacking.

An engineer applies a tile to Columbia's left wing.

The external tank for STS-1 arrives at the Kennedy Space Center, July 1979.

Left: Engineer applying a tile to Columbia's left wing. Right: The ET for STS-1 arrives at KSC.

Boosters and engines

All the components of the two Solid Rocket Boosters (SRBs) were in the VAB by September 1979, and stacking began. By early January 1980 both were stacked on the Mobile Launch Platform. To qualify the boosters, workers fired the motor four times for demonstration and three times for qualification at Thiokol's Wasatch Facility near Brigham City, Utah. After the final test on Feb. 13, 1980, managers qualified the booster for flight.

Stacking of the STS-1 solid rocket boosters in the Vehicle Assembly Building.

An SRB in place for the final qualification static firing.

An SRB during the final qualification static firing in Utah.

All three Space Shuttle Main Engines passed flight qualification and were installed in August 1979. At the National Space Transportation Laboratory in Bay St. Louis, Mississippi, workers ran 3-engine tests with non-flight-qualified engines:

DateResult
Dec. 17, 1979First full-duration test, 554 seconds
Feb. 1, 1980Ended after 4.6 seconds because one engine started late
Feb. 28, 1980Repeat, the second of a planned series of seven, ended successfully after 560 seconds

Workers install one of Columbia's main engines.

The Dec. 17, 1979, 3-engine test at the National Space Transportation Laboratory.

Tests and simulations

Several hundred NASA and contractor engineers at KSC, Johnson Space Center (JSC) and Rockwell's Downey, California, facility ran Orbiter Integrated Tests (OIT) to exercise orbiter hardware and software through a mission timeline. The first, from Dec. 16 to 20, 1979, included Columbia's first simulated launch and flight into orbit. Prime crew John W. Young and Robert L. Crippen and backups Joe H. Engle and Richard F. Truly took part from inside Columbia, powered up in the OPF. A second, 11-day OIT with five simulated launches and a full 54-hour simulated flight finished successfully on Jan. 18, 1980. Crippen called the shuttle "a really spectacular machine," and Young said Columbia performed "like a champ."

STS-1 prime crew Crippen and Young arrive at the OPF for the OIT.

Starting Jan. 24, flight controllers and astronauts also ran a 30-hour simulation from Mission Control at JSC, from a simulated launch and orbital insertion to a simulated landing the next day. About 500 NASA and contractor personnel took part, and the aim was to test operations and procedures over an extended period. More simulations followed at regular intervals.

Sources

Comments

Spinner Logo

More on Science

By Hub Nexus editors
Top 10 in AI, week of 26 October 2026
By Hub Nexus editors
Top 10 in AI, week of 19 October 2026
By Hub Nexus editors
Top 10 in AI, week of 12 October 2026
By Hub Nexus editors
Top 10 in AI, week of 2 November 2026
CC0 1.0 (public domain)
Delta 2020 Intensifies into a Major Hurricane